City Hall and most offices/facilities will be closed on November 28th and 29th. Emergency services remain available 24/7. Happy Thanksgiving!

1/11/2019 – 2017 Storm Damage Repairs: 70 Irwin

Posted on January 11, 2019


Storm Damage Repair

The City’s contractor Valentine Corporation has winterized the slope and maintained the plastic tarps and other erosion control measures throughout the couple of rain storms. The contractor is going to start rebuilding the slope above the first concrete retaining wall next week in anticipation of drilling the piles for the last and largest concrete retaining wall in the project. The project is expected to be complete in mid-February.

Storm Damage Repair Storm Damage Repair

Close window