City Hall and other offices will be closed to the public from December 23 to January 3, but appointments are available upon request. Public safety and emergency services remain available 24/7.  

2020 Sewer Replacement Phase 2 – Weekly Update April 26th

Posted on April 26, 2023


Project Update

Replaced sewer main and sewer laterals and temporarily paved sewer laterals on Clayton St

The contractor will replace sewer main and sewer laterals on 1st St between B St and C St from April 28th to May 19th.

The contractor will replace sewer main and sewer laterals on 2nd St and East St from May 15th to May 29th.

Close window