City Hall and other offices will be closed to the public from December 23 to January 3, but appointments are available upon request. Public safety and emergency services remain available 24/7.  

2020 Sewer Replacement Phase 2 – Weekly Update August 22

Posted on August 22, 2023


Project Update

Replaced sewer main and sewer laterals on Woodland Ave, Irwin St, and Duffy Pl

The contractor replaces sewer main and sewer laterals on Locust Ave from August 7 to September 1st.

The contractor replaces sewer main and lower laterals on Ivy Ln from August 22 to September 1st.

Close window