Updates to City Hall Hours on Fridays in July and August 

Excessive Heat Warning in effect until next Tuesday. Red Flag Warning is in effect until Friday evening. For information on how to stay safe in the heat and prevent wildfires please visit emergency.marincounty.org

 

2020 Sewer Replacement Phase 2 – Weekly Update March 27

Posted on April 6, 2023


Project Update – Week of 3/27

Replaced sanitary sewer mains and laterals on  on 1st St from Shaver St to Welch St. 

Replaced sanitary sewer mains and laterals on  Welch St and on 1st St from Clayton St to 1st St. 

Sewer Main replacement on Clayton St from Welch St  is between 4/6  to 4/21.  Road closure is on Clayton St.

Final street paving  of  1st St, Frances St, E St, Clayton Ave, and Welch St is scheduled from April to May 2023.

Close window