As of January 10th, the following locations have been completed:
- Madrona Street
- Billou Street
- Edgewood Way
- McCoy Road,
- 4th St and C St.
- Bayo Vista Way
- Terradillo Easement between Marinita Ave and Terradillo Ave.
- 4th St. between Mary St and Grand Ave.
The following work is scheduled to take place over the next month:
- West Crescent Ave Easement: The installation of the sewer mainline is taking place January 6th– January 14th, the reconnections of the laterals will begin shortly after.
- Grove Street: The reconnection of the sewer mainline to manhole will tentatively take place January 15th – January 22nd
- Neame Ave Easement : The sewer mainline installation and lateral reconnections will be taking place on January 20th through January 31st.
- Oakhurst Ave: The rehabilitation of the mainline will be taking place January 31st through February 12th.