City Hall and other offices will be closed to the public from December 23 to January 3, but appointments are available upon request. Public safety and emergency services remain available 24/7.  

2023 Sewer Pipe Burst – Update November 1

Posted on November 1, 2023


Project Update

Replaced sewer main and lower laterals on Highland Ave starting at Jewell Street to approximately 400 feet east up Highland Ave.

Replaced sewer main and lower sewer laterals on Spring Grove Ave between Greenfield Avenue and Terrace Avenue from September 30th to October 20th.

Replacing sewer main and installing cleanout and backflow prevention devices on Scenic Ave starting from 96 Scenic Ave approximately 400 linear feet East to 18 Thomas Street from October 16th to November 1st.

Our contractor will replace sewer main and install cleanout and backflow prevention devices on W. Crescent Ave from November 1st to November 17th.

 

 

Close window