2023 Sewer Pipe Burst – Update September 28

Posted on September 28, 2023


Project Update

Replacing sewer main and lower sewer laterals on Alexander Ave starting from W Crescent Dr including 78 to 40 Alexander Ave and the sewer pipes in sewer easement from 16 Alexander to 7 Alexander Ave from September 21st to October 6th.

Replacing sewer main and lower sewer laterals on Glen Park Ave near 140, 150, 154, 158, and 162 Glen Park Avenue and on Highland Avenue near properties 4 and 7 Highland Avenue where Jewell Street intersects with Highland Avenue from September 25th to October 6th.

Replace sewer main and lower sewer laterals on Pearce Ave from October 2nd to October 11th.

 

 

Close window