Third Street Improvement Project – 11/18/2022 weekly update

The City of San Rafael will be sending out weekly project updates with construction updates, traffic closure updates, and other relevant information for this project. To receive these updates, please sign up using the form at the left-hand side of the project website. THIS WEEK (November 14 – 18): Construction Crews formed the stairs and … Continued

Dredging to continue in San Rafael Canal: Boater Safety Precautions

Dredging will soon continue in the San Rafael Canal in the coming days. Please keep in mind the following Boater precautions: Boaters must exercise caution when passing the dredge in the channel. The Dredge DB‐Beaver is available on Channel 80 and slacks its anchor wires for vessel traffic in and out of the channel. The … Continued

Third Street Improvement Project – 11/04/2022 weekly update

The City of San Rafael will be sending out weekly project updates with construction updates, traffic closure updates, and other relevant information for this project. To receive these updates, please sign up using the form at the left-hand side of the project website. THIS WEEK (October 31 – November 4): Construction crews formed the stairs … Continued

Bayside Acres Phase A – Weekly Update October 31st

Project Update – Week of 10/31 WR Forde is continuing efforts to trench through the bottom half of Oak Dr. All residents can expect the lower section of Oak Dr. to be busy as they drive their excavator through the street. Flaggers will be monitoring the entry into Oak Dr. and directing traffic. Residents can … Continued

Bayside Acres Phase A – Weekly Update October 24th

Project Update – Week of 10/24 WR Forde has returned to the top of Oak Dr. to complete work on the manhole. This week they’ll have reduced construction presence along the street to allow for more residential traffic to flow. Two flaggers will be stationed at either side of Oak Dr. to direct all residents. … Continued

Third Street Improvement Project – 10/27/2022 weekly update

The City of San Rafael will be sending out weekly project updates with construction updates, traffic closure updates, and other relevant information for this project. To receive these updates, please sign up using the form at the left-hand side of the project website. THIS WEEK (October 24 – October 28): Crews replaced sidewalk sections at … Continued

Bayside Acres Phase A – Weekly Update October 17th

Project Update – Week of 10/17 WR Forde is completing the work on Marine Dr. this week. They will still be using Marine Dr. as their main path of travel. Residents should continue to work with the onsite flaggers as they drive through the area. At the start of next week, WR Forde will return … Continued