Updates to City Hall Hours on Fridays in July and August 

 

Author: admin

Public Works and Parking Services Team Up to Save You Time!

City Employee: What’s that? You’re applying for an encroachment permit (EP)? Resident/Contractor: Yes, we’ll be painting, and we’ll need to place scaffolding on the sidewalk, I think we’ll need to take up two parking spaces as well. City Employee: Okay, you’ll need to apply for the EP here, jump through a ring of fire, tame … Continued

Uncontrolled Crossing Evaluation and Prioritization

The Traffic Division is completing an assessment of uncontrolled crossings throughout the City and we will be chipping away at improvements now through summertime. An uncontrolled crosswalk is anywhere there is a marked crosswalk and cross traffic does not have to stop except for when a pedestrian is present. In this initial assessment, we studied … Continued

Update: SMART Larkspur Extension – Phase 1 Near Completion

The SMART Larkspur Extension construction work on the Francisco Blvd. West realignment and Phase-1 of the Multi-Use Path (from Rice Street to Andersen Drive) is rapidly nearing completion.  The section of roadway from 2nd Street to Irwin Drive was opened for traffic earlier this month. The Francisco Blvd. West and Rice Drive intersection, where the … Continued

Public Safety Center – Update 2/22/2019

The Public Safety Center construction team has been finding ways to make progress and work around the storms.  Currently, most of the structural steel has been erected and the metal framing has started at the ground level.  The electrical, plumbing, and mechanical subcontractors have been working in the basement.

Fire Station #57 – Update – 2/22/2019

Fire Station #57 construction of interior walls is underway.   Sheetrock continues to be installed and the contractor is moving toward mechanical, electrical and plumbing inspections before closing the walls.  They are also chipping away at the site work while maximizing their efforts on every clear day that they can get.  Despite the heavy rains, they … Continued

Fire Station 52 – Project completion is approaching

The Contractor has been working in the rain and on the weekends to complete our new Fire Station 52.  They are installing interior finishes and completing testing and commissioning of equipment.  They will be pouring the last portion of the approach, curb, and sidewalk by the end of next week.  Pavers, side gates and planting … Continued

Terra Linda Community Center: New Floor

The Terra Linda Community Center (TLCC) is receiving new flooring in their main auditorium.  The work is expected to be completed this week and we’re very happy with how it’s turning out.  We went with a very durable vinyl product that we expect to last 15 to 20 years.  Despite a few minor initial bumps … Continued

Storm Patrol: Tree Down

Public Works employees Aaron Tubbs and Jim O’Hagan got a call about a fallen tree at 3:00 am on February 14th while working overnight during the storm. They found this in the roadway near Grand Ave and Villa Ave.  A temporary detour was set-up until the tree contractor was able to clear the road.

Storm Response: Weathering the Storm

Last Wednesday & Thursday San Rafael received almost 8” inches of rainfall in a 24-hour period over. On Wednesday evening our rain gauge displayed nearly 15 inches of rainfall for the year, 6 of those inches had been collected last 24 hours of that reading. Crazy!!! Crews from San Rafael Public Works worked around the … Continued

Albert Park Play Area Improvements

The City’s contractor M3 Integrated Services has installed the playground equipment and is on track to install the resilient rubber surfacing the first week of March. Next week they will be working on the sidewalk between the Marin Bocce Federation and the B Street community center.