Marin Magazine has launched their 2019 Best of Marin County survey, which showcases the most popular dining, entertainment, and services establishments across Marin. Do you have a favorite bookstore, coffee shop, restaurant, or fitness and recreation place? Well, now’s your chance to show these local businesses some love by voting for them in the 2019 … Continued

Weekly Weather Update from the National Weather Service

Synopsis We should expect lingering rain showers this morning with a drying trend into the afternoon today.  Drier conditions should prevail until early evening tomorrow where an atmospheric river is predicted to arrive bringing heavy rain and strong winds.  This storm is predicted to bring about 2.65-inches of rain between 4PM Tuesday to 10PM Wednesday.  … Continued

2/08/2019 – City Hall Switch Gear Replacement

The City’s contractor Cal Elite Builders has been working diligently on installing the new PG&E primary line for the new transformer that will sit adjacent City Hall. They have also been placed 40 electrical vehicle (EV) charging station conduits for the 2 EV charging stations as well as future EV charging stations throughout the upper … Continued

2/08/2019 – Pickleweed Park Playground Equipment Replacement

The City received a federal grant for the replacement of playground structures at Pickleweed Park. The project will remove the existing swings, slides, accessory structures, & sand which have been there for some 20 years and replace them with brand new structures & fill the play area with engineered wood fiber. We have conducted online … Continued

2/08/2019 – Albert Park Play Area Improvements

The City’s contractor M3 Integrated Services poured the first of sidewalk this week and they have also started to assemble the playground equipment. The park is scheduled to open in April.  

2/08/2019 – 2017 Storm Damage Repairs: 70 Irwin

The City’s contractor Valentine Corporation has started rebuilding the slope above the lower concrete wall. The project has been plagued with weather delays and wet soil which has pushed the opening of Upper Irwin back to late April.

2/08/2019 – SMART Update: Partial Opening

On Thursday, February 7th, SMART’s contractor opened the portion of Francisco Blvd West between 2nd St and Irwin St. This partial opening will reduce the impact to businesses located on Irwin St and allow traffic to more easily access the freeway. SMART’s contractor continues to coordinate with the Marin Municipal Water District regarding the installation … Continued

2/08/2019 – Grand Avenue Update: Sidewalk and Railing

The City’s contractor, Valentine Corp, has completed work on the west side of the Grand Ave vehicle bridge by installing a new sidewalk and barrier railing. Vehicle traffic has been shifted, again, such that the contractor is in the process of removing the existing sidewalk on the east side of the vehicle bridge. A new … Continued

Richmond-San Rafael Bridge (I-580) Closed in Both Directions

The Richmond-San Rafael Bridge is closed in both directions due to structural problems. There is no estimated time to reopen the bridge. Expect delays and use alternate routes to avoid the area. For updates, visit 511.org. To sign up for urgent alerts, text your zip code to 888777 or visit www.nixle.com.