Project Update Replaced sewer main and sewer laterals on Elford St, Willow St, Jordan, and Locust St. The contractor replaces sewer main and sewer laterals on Lincoln St, Irwin St, and Duffy Street from July 10th to August 11th. The contractor will restore paving on El Camino Ave from July 17th to July 18- and … Continued
Project Update The contractor replaced sewer main and sewer laterals and temporarily paved on Jordan St and Locust St The contractor is replacing sewer main and sewer laterals on El Camino Drive from June 22th to June 30th The contractor replaces sewer main and sewer laterals on Ivy Lane and Marten Blvd from July 3rd to … Continued
Project Update Replaced sewer main and sewer laterals and temporarily paved the road on 1st St and C St The contractor replaces sewer main and sewer laterals on Tayler St and C St from May 18th to June 2nd. The contractor will replace sewer main and sewer laterals on Elford St and Willow St from … Continued
Project Update The contractor replaces sewer main and sewer laterals on 1st St between B St and C St from April 28th to May 19th. The contractor will replace sewer main and sewer laterals on 2nd St and E St from May 22th to June 6th.
Project Update Replaced sewer main and sewer laterals and temporarily paved sewer laterals on Clayton St The contractor will replace sewer main and sewer laterals on 1st St between B St and C St from April 28th to May 19th. The contractor will replace sewer main and sewer laterals on 2nd St and East St … Continued
Project Update Replaced sewer main and sewer laterals and temporarily paved sewer laterals on Clayton St The contractor will replace sewer main and sewer laterals on 1st St between B St and C St from April 28th to May 26th.
Project Update – Week of 3/27 Replaced sanitary sewer mains and laterals on on 1st St from Shaver St to Welch St. Replaced sanitary sewer mains and laterals on Welch St and on 1st St from Clayton St to 1st St. Sewer Main replacement on Clayton St from Welch St is between 4/6 to 4/21. … Continued
Project Update – Week of 2/20 WR Forde completed sanitary sewer main replacement on Marin St from Clayton Ave to Ross St. Sewer laterals on Marin from Clayton Ave to Ross St will be replaced and expected to be completed by February 24th. From 2/20 – 3/10, WR Forde will be on Clayton Ave and … Continued
This project is complete and was a great success. The scope of the project was to lower the sewer-main pipes in Octavia Street, Woodland Avenue and in B Street between Warner Court and 1st Street. This allowed the District to relocate a failing sewer-main serving residences on Woodland Place, and connect a new sewer-main installed … Continued
Due to weather conditions, some final work items on this project were delayed. Final work involves surface work to include minor paving and striping. The Contractor anticipates completing everything by mid-January 2022.