B St. Culvert Replacement Project: February Update

Posted on February 9, 2024


The B Street Culvert Replacement Project aims to replace a section of the current concrete box culvert under B Street, near Woodland Avenue. Although City council awarded the construction contract to Maggiora & Ghilotti, Inc. on October 18, 2021, the project faced delays due to heavy storms that year. Subsequently, negotiations with the City concerning protection methods for the
nearby PG&E pole led to further postponement. Eventually, increased material costs and scheduling conflicts prompted Maggiora & Ghilotti to request contract termination. On April 17, 2023, City Council authorized the termination. Currently, City staff is planning to rebid the project and to return to Council in Spring 2024 for consideration of a new construction contract.