Homelessness Update Community Meeting, October 3, 2024, via Zoom; click here for more information.

B St. Culvert Replacement Project: Update & Upcoming Street Closure on 9/10/24

Posted on September 3, 2024


B Street Culvert

Construction on the B Street Culvert Replacement Project started on July 22, 2024.

The section of the current concrete box culvert requiring replacement has been replaced as of August 30, 2024.  This week, the contractor will pour the curb, gutter, sidewalk, and ramps. Next week, the contractor will resurface the section of B Street around the work area.

Note that the resurfacing work will require full road closure at the B Street intersection next to Taylor Street, Bayview Street, and Woodland Avenue.

Street resurfacing is currently scheduled to occur on September 10, 2024. The plan is to finish the job with striping taking place on the week of September 16, 2024.

Close window