Bungalow Avenue – construction at loop nearing completion!

Posted on May 2, 2022


.

Construction work on the Bungalow Ave loop is almost at the finish line!  The City’s contractor, Ghilotti Bros Inc. (GBI) began work on the final section of concrete work on April 27th, 2022.  The City has also entered into an agreement with Precision Concrete to shave offsets in the vehicular concrete, reducing hazards along the road for vehicles and pedestrians alike.  Precision Concrete’s work will follow once GBI is finished and will require minimal traffic control, allowing the neighbors full access to their greatly improved roadway!  Designs are currently being finalized for the lower section of Bungalow Ave from Woodland Ave to Picnic Ave which will be resurfaced and widened later this summer. This project involves removing the steep gutters to improve safety for all user’s pedestrian and vehicle alike. The schedule is dependent on PG&E coordination for the relocation of a power pole which they estimate to be ready mid-Summer.

.