City Hall and other offices will be closed to the public from December 23 to January 3, but appointments are available upon request. Public safety and emergency services remain available 24/7.
A temporary sidewalk closure at Point San Pedro Road between Peacock Drive and Knight Drive will be necessary to continue with construction of the Fire Station 55 Renovation to maintain pedestrians’ safety, Fire Department response times and to accommodate the needs of the construction project. WHAT TO DO: Cross safely at the designated crosswalks & … Continued
Construction continues at two new fire stations Now that concrete placement of the elevator tower is complete at Fire Station 54, construction has continued into the living quarters. Wickman Development and Construction has the framework for the living quarters well underway with structural walls and interior walls complete. The second story of the building is … Continued
Contact: A. Fabiola Guillen, Sr. Project Manager – Public Works Construction continues at the two fire stations. At Fire Station 54, Wickman Development and Construction, construction is well underway with wall framing and the concrete placement of the elevator tower. The work was successfully completed last Thursday. This is a critical milestone that will … Continued
A lot of progress has been made in the last couple of weeks at the two fire station construction sites. At Fire Station 54, Wickman Development and Construction, had been working on footing rebar installation for a few weeks leading up to a large concrete pour last week. The concrete pour included the new building pad … Continued
Currently, Wickman Development & Construction is rebuilding the apparatus bays and living quarters of the two fire stations. Fire Station 54 spread footing foundations have finished installation in the new portion of the building where the living quarters will be. Excavation of the elevator pit has finished, and the walls of the elevator shaft are now … Continued
On April 19, the City held two groundbreaking ceremonies for the fire station reconstruction project: one for Fire Station 54 and one for Fire Station 55. A line of shovels was used to officially mark the start of the renovations. Mayor Kate Colin was joined by Vice Mayor Kertz, Councilmembers Bushey and Llorens Gulati, Fire … Continued
On Tuesday, April 19, Castro Avenue from Francisco Boulevard East and Bellam Boulevard will be closed from 3:30 – 5:30 pm for the Fire Station 54 groundbreaking ceremony. NO parking signs will be posted along both sides of Castro Avenue between Francisco Boulevard East and Bellam Boulevard. Only cars of attendees will be allowed to … Continued
Changed westbound Lane closure and bike lane relocation during construction of Fire Station 55 EXTENDED LANE LIMIT – Point San Pedro Road between Riviera Drive and Knight Drive The originally planned westbound lane closure from Peacock Drive to Knight Drive has been updated due to safety and accessibility concerns. The westbound lane closure will start … Continued
Fire Stations 54 & 55 – Foundation work Our fire station contractor, Wickman completed demolishing the old buildings and gutted the apparatus bays for retrofit and renovation. Wickman also completed over excavation and compaction to prepare the building pad. Currently, they are building the foundations and underground utilities at both sites. Fire Station 54 spread … Continued
The City issued Notice to Proceed with construction to Wickman Development and Construction on January 10, 2022. Since then, Wickman, our General Contractor, has prepared the two project sites for construction. Perimeter fences, safety notices, and field offices were installed. Wickman’s demolition subcontractor mobilized into Fire Station 54, located at 46 Castro Ave. The living quarters at Fire Station 54 have been … Continued