Category: Essential Facilities

Public Safety Center | March 2018 Update – Pumping Rain Water

During the month of March, the weather turned for the worst raining constantly pushing the site to its limits forcing the team to act quickly. An additional baker tanks was brought to the site and the purchase of pumps was required to help contain the rain water on site. The pumps had to be placed … Continued

Fire Station 57 Update February 2018

Project Update The team has made excellent progress at Fire Station #57. During the month of January, the new driveway and side walk were completed along Civic Center Drive. The foundation formwork and rebar are underway as well as the elevator pit concrete work.  We are excited to see this project moving at full speed. … Continued

Fire Station 52 Update February 2018

Project Progress Alten Construction continues to work on the Fire Station and Classroom Buildings.  At the Fire Station Building, the CMU walls are going up along with electrical and plumbing rough in work.  At the Classroom Building, the Contractor continues their wood framing and electrical rough in.  The Contractor also completed the concrete work for … Continued

Fire Station 57 Update January 2018

Project Update: During the month of January, Alten Construction continued to work on the Fire Station Building; the Classroom Building and the retaining wall/ bio-retention on the North-East side of the site. At the Fire Station Building, contractor continued with installation of Scaffolding, wood framing at the bay room and the CMU Block. The CMU … Continued

Fire Station 52 Update January 2018

Project Update: During the month of January, Alten Construction continued to work on the Fire Station Building; the Classroom Building and the retaining wall/ bio-retention on the North-East side of the site. At the Fire Station Building, contractor continued with installation of Scaffolding, wood framing at the bay room and the CMU Block. The CMU … Continued

Lease Revenue Bonds

$46,300,000* San Rafael Joint Powers Financing Authority Lease Revenue Bonds, Series 2018 (Public Safety Facilities Project) (Green Bonds) Anticipated date of offering on or about March 14, 2018 The offering of Bonds will be made only by the Preliminary Official Statement, which describes the security for such issue and which may be obtained in any … Continued

Public Safety Center Update February 2018 – Notice to Proceed Cleared

Great news! The Public Safety Center notice to proceed will be issued next Monday, February 5.  The site is completely cleared, the office trailers have been dropped off, and the contractor’s A team is ready to go.  The pre-construction meeting took place this week where Police and Fire Chiefs expressed their excitement for this new … Continued

Fire Station 57 Update November 2017

Project Progress During the month of November, Alten Construction substantially completed all excavation activity for the new storm drain. Form work and concrete pours for all manholes and inlets continued throughout the month. Temporary storm drain bypass measures were maintained and a secondary bypass pump was removed due to decreased rainfall. The review and processing … Continued

Fire Station 52 Update November 2017

Project Progress During the month of November, Alten Construction continued to work on the Fire Station Building; the Classroom Building and the retaining wall/ bio-retention on the east side of the site. At the Fire Station Building, the contractor continued with the  excavation and installation of all under slab utilities and water-proofed the elevator pit. … Continued

Fire Station 57 Update September 2017

Project Progress During the month of September, Alten construction completed site preparation for the next phase of work, which will include the installation of the underground site utilities and the building foundation work. Alten Construction also completed the foundation, rebar installation, and block placement for the CMU wall that is located at the perimeter of … Continued