Project Progress During the month of June, Alten Construction completed the CMU installation for the Apparatus Bay. Steel elements (in conjunction with CMU activities) were completed for the Living Quarters. Embedded MEP elements were completed and the concrete slab was poured for the Apparatus Bay and Living Quarters. Shop fabrication for remaining steel commenced. Potholing … Continued
Project Progress During the month of May, Alten Construction work progressed on the Fire Station Building, the Training Classroom and the Training Tower. The Tower erection began the first of May and neared the structure 50’ top out at the end of the period. The Classroom stucco system brown coat was applied and completed the … Continued
Project Progress During the month of May, Alten Construction completed the slab on grade for the Office and Living Quarters areas. CMU installation for the Utility Rooms was completed and continued for the Apparatus Bay and Living Quarters. The installation of steel elements (ledgers and columns) continued for the Living Quarters. Installation of supports for … Continued
Intersection of Laurel Place and Wilkins Street: Streets Maintenance Crews installed a new crosswalk ladder and STOP Sign on the Wilkins side. Laurel Place has been a hotspot for speeding, so these new intersection improvements will provide increased safety for pedestrians. Fire Station 54 got new KEEP CLEAR in front of the station to prevent … Continued
Project Progress During the month of May, Alten Construction continued with the excavation of footings, elevator pits / stairs, and underground utilities (storm drain, fire line, sewer, waterlines, electrical and any sleeves required for future plumbing). After review /acceptance of the footing excavations by the geotechnical engineer, the contractor installed all the conduits and rebar … Continued
Project Update During the month of April, Alten Construction completed the installation of under-slab rough electrical and plumbing elements, and also completed the placement of underslab rock and vapor barrier at the Living Quarters. CMU installation continued at the Apparatus Bay and Utility Rooms. Selected steel elements (ledgers and columns) and steel door frames were … Continued
Project Update During the month of April, Alten Construction continued work on the Fire Station Building, the Training Classroom and the Training Tower. The Training Tower foundation slab on grade was placed mid-April. The Tower structure design submittal was approved and in early May the Tower erectors will be on site to begin erection. The … Continued
During the month of April 2018, the weather cleared up allowing Alten to initiate the off haul of the clean material, contaminated material and prepare the building pads for certification. Hauling off of the clean material was a success hauling off approximately 2,500 cubic yards to the airport. During the excavation of the contaminated material … Continued
Project Update: During the month of March, Alten Construction mobilized material and equipment and began installation of CMU at the perimeter and interior building walls. The installation of UG MEP elements (including deep interior and Apparatus Bay trough drain aspects) was completed. Delivery, staging, and set up of CMU material and equipment continued during the … Continued
Project Update: During the month of March, Alten Construction continued work on the Fire Station Building and the Training Classroom. The Training Tower foundation work initiated with anchor pier delivery, installation and successful pull-testing. Tower footing rebar installation was ongoing at the end of the period. At the Fire Station Building, the CMU block was … Continued