Written by: JC Agcaoili, Assistant Engineer Planting is now complete at the Spinnaker Point Parking Modification project and the striping has been laid out. Final striping will be installed on Friday, March 23rd, weather permitting. We look forward to opening the parking spaces to the public as we understand how important additional parking is to … Continued
JC Agcaoili, Assistant Engineer Final paving and concrete work is now complete on the Department of Public Works’ Spinnaker Point Parking Modification project. The remaining operations for the project will be the planting and striping of the new parking spaces. The current forecast is still showing some rain which will impact the days during which … Continued
The Canal Area Parking Taskforce recommended the consideration of Windward Way to provide secure on-street and overnight parking. The City team made significant progress in designing a visual concept and further explanations of how that concept would function to achieve the ultimate goals. The implementation of this idea would require a significant initial investment by … Continued
The evaluation of the T’s and L’s parking markers for both Spinnaker Point and Baypoint Village roadways have been completed. The objective is to maximize the number of vehicle parking spaces with the installation of T’s and L’s pavement markings. This approach would add a net gain of 41 additional parking spaces. The work will … Continued
Construction is almost complete on the Department of Public Works’ Spinnaker Point Parking Modification Project. Our contractor, Michael Paul Co., expects all major construction operations, such as concrete and asphalt, to be complete within the next two weeks. The current forecast shows some rain and cold temperatures ahead. Due to this weather forecast, we have … Continued
Construction is almost complete on the Department of Public Works’ Spinnaker Point Parking Modification project. Our contractor, Michael Paul Co., expects all major construction operations such as concrete and asphalt to be complete within the next two weeks. The current forecast shows some rain and cold temperatures ahead. Due to this weather forecast, we have … Continued
PG&E’s subcontractor, Pinnacle Power Services Inc., will be performing electrical utility work by 46 Castro Ave on Saturday, 1/28 from approximately 10 P.M to 6 A.M. The work requires the power to be turned off in the area so work is happening at night to minimize impacts to the neighboring businesses. The road will not … Continued
Construction for the Spinnaker Point Park Modification project began on Monday, October 10th. The initial construction stages of the project include demolition of the existing sidewalk and grading of the adjacent landscape. Environmental measures have been put in place to protect the local wildlife in accordance with environmental regulatory permits. The project has a projected … Continued
One of the big transportation issues in the Canal neighborhood is the on-street parking supply that can’t keep up with the parking demand. With the help of W-trans, and in collaboration with Parking Services, the area has been studied and assessed for potential improvements. After changing the parking time limits to 24 hours in the … Continued
One of the big transportation issues in the Canal neighborhood is the on-street parking supply that can’t keep up with the parking demand. With the help of W-trans, and in collaboration with Parking Services, the area has been studied and assessed for potential improvements. After changing the parking time limits and getting the ability to … Continued