11/11/18 – 2017 Storm Damage Repairs Update – 70 Irwin

The City’s contractor Valentine Corporation has nearly completed the work in the backyards on Glenaire Drive and they have started working on the third retaining wall on the hillside. The City is building a series of four retaining walls to stabilize the hillside and protect Irwin street during future winter storm.    

11/9/18 – Essential Facilities – The Transformation is Evident!

Fire Station #52  If you’ve driven by any of the Essential Facilities projects, you have seen the undeniable transformation that the City of San Rafael is going through. At Fire Station #52 the Training Tower, the Training Classroom and the Fire Station buildings are very close to completion. In the last few months, the contractor … Continued

San Rafael Transit Center Environmental Work Begins

The Golden Gate Bridge, Highway and Transportation District (Golden Gate Transit) has started a multi-year process to develop a new transit center for San Rafael. The current transit center will be affected by the extension of Sonoma-Marin Area Rail Transit (SMART) system to Larkspur. Several government agencies, including the City of San Rafael, are partnering to identify a new … Continued

11/1/18 – Stormwater Inspections in Action

It’s that time of year when our Department of Public Works staff come out to clean the City’s storm drains and headwalls before the rainy season begins. This is the second year that our staff members are using a smartphone app to keep track of inspections completed and and drains cleaned. The app combines a … Continued

10/31/18 – Central San Rafael 101 NB Off-ramp Replacement

TAKE THE SURVEY (survey closed) Caltrans San Rafael 101 NB Off-ramp Presentation   Caltrans intends to rebuild the bridge that makes up the northbound 101 Central San Rafael highway off ramp.  The reason for this work is that the existing structure is inadequate so the entire bridge will be replaced over a large part of … Continued

10/19/18 – Sidewalk Repair Program Update

As of 10/18/2018, Van Midde Concrete has sent out 170 proposals to participating property owners. That means all but 30 property owners in the program have now received their final proposals. Of those 170 proposals sent out, the City has received now 125 back signed from property owners. We are almost there! Once the signed … Continued

10/19/18 – Grand Avenue Pathway Connector Project

The Grand Ave Pathway Connector project contractor, Valentine Corp., began work by performing exploratory field work on the former Marin Motors site at 750 Grand Ave. To our surprise, we located existing concrete and steel sheet piles buried under the asphalt in the location of the new bridge abutment. The design team is working hand … Continued

10/18/18 – Landslide Repair – 70 Irwin

Work is moving quickly at 70 Irwin; this week the City’s contractor Valentine Corporation started installing MSE block walls at the bottom of the hillside that was also the scene of a landslide during the winter of 2017. Installation of these two block walls marks the beginning of the long-awaited hillside restoration.

10/19/18 – Mudslide Repair – 80 Upper Toyon

This week the City’s contractor Maggiora and Ghilotti finished installing a CIDH retaining wall and repaving the roadway at 80 Upper Toyon. This project was designed to support the roadway after a mudslide happened downhill of the road in the winter of 2017. FEMA and Cal-OES will reimburse the City the majority of the cost … Continued

10/19/18 – Grate Repair

Fall has arrived and the North Bay had its first rainfall of the year earlier this month – with over a 1” of rain. Crews from the Street Division performed an emergency repair to the grates that protect large items from entering the storm water pump station located at 400 Canal Street. Within a four-hour … Continued