Third Street Improvement project – 3/18/22 weekly update

The City of San Rafael will be sending out weekly project updates with construction updates, traffic closure updates, and other relevant information for this project. To receive these updates, please sign up using the form at the left-hand side of the project website. THIS WEEK (March 14 – 18): The City’s contractor, Maggiora & Ghilotti, … Continued

Wilhelm: Notice of Tree Work Monday 3/21/22 – Friday 3/25/22

Wilhelm tree crews are slated to work along PG&E powerlines at the following locations in your jurisdictions starting MONDAY 3/21/22 thru FRIDAY 3/25/22   50 ACACIA AVE 3 AQUINAS DR 44 AQUINAS DR 37.996798 -122.506255 AQUINAS FIRE RD 37.997104 -122.505 AQUINAS FIRE RD 37.997441 -122.504561 AQUINAS FIRE RD 37.997644 -122.504561 AQUINAS FIRE RD 37.99108 -122.500253 … Continued

Third Street Improvement project – 3/11/22 weekly update

The City of San Rafael will be sending out weekly project updates with construction updates, traffic closure updates, and other relevant information for this project. To receive these updates, please sign up using the form at the left-hand side of the project website. THIS WEEK (March 7 – 11): The City’s contractor, Maggiora & Ghilotti, … Continued

March 2022 Update – Extended Lane Limit: Notice Of Lane Closure And Bike Lane Relocation During Construction Of Fire Station 55 Renovation

Changed westbound Lane closure and bike lane relocation during construction of Fire Station 55 EXTENDED LANE LIMIT – Point San Pedro Road between Riviera Drive and Knight Drive The originally planned westbound lane closure from Peacock Drive to Knight Drive has been updated due to safety and accessibility concerns. The westbound lane closure will start … Continued

Wilhelm: Tree Work MONDAY 3/14/22 – FRIDAY 03/18/22

Wilhelm tree crews are slated to work along PG&E powerlines at the following locations in your jurisdictions starting MONDAY 3/14/22 thru FRIDAY 3/18/22.     50 ACACIA AVE 3 AQUINAS DR 44 AQUINAS DR 37.996798 -122.506255 AQUINAS FIRE RD 37.997104 -122.505 AQUINAS FIRE RD 37.997441 -122.504561 AQUINAS FIRE RD 37.997644 -122.504561 AQUINAS FIRE RD 37.99108 … Continued

Fire Station 54 & 55 Construction update

Fire Stations 54 & 55 – Foundation work Our fire station contractor, Wickman completed demolishing the old buildings and gutted the apparatus bays for retrofit and renovation. Wickman also completed over excavation and compaction to prepare the building pad.   Currently, they are building the foundations and underground utilities at both sites. Fire Station 54 spread … Continued

Park irrigation system repairs and upgrades

Parks Division staff have been making repairs to irrigation systems throughout the City in preparation for the watering season. With some watering restrictions lifted, Parks staff will start irrigating areas that they could not during the stricter conditions. Most of the City’s irrigations systems are beyond their usable life and require constant attention to prevent … Continued

Taking advantage of the sunny weather for needed repair work

The sunny weather has allowed Streets staff members to catch up on much needed maintenance and repairs. In the photo you will see Streets Lead Worker Arturo Tinoco repairing a drainage bubble out that is in the curb. These often become broken over time, usually from being driven over by heavy trucks, which causes them … Continued

Third Street Improvement project – 3/4/22 weekly update

The City of San Rafael will be sending out weekly project updates with construction updates, traffic closure updates, and other relevant information for this project. To receive these updates, please sign up using the form at the left-hand side of the project website. THIS WEEK (February 28- March 4): Maggiora & Ghilotti worked on locating … Continued