Category: Bungalow Avenue from Woodland Avenue to La Loma Court

Bungalow Ave project update

Construction work on the final section of the Bungalow Ave project began late last month.  This section of Bungalow Ave being reconstructed is the area between Woodland Ave and Picnic Ave, often referred as “lower Bungalow.”   The City’s contractor, Ghilotti Bro’s Inc (GBI) has been making great progress.   GBI has been accommodating folks in the … Continued

Bungalow Ave project update

Construction on the lower Bungalow Ave. section from Woodland Ave. to Picnic Ave has started this week.  This project will extend the current width of the roadway, while removing steep gutters, improving the overall safety of the street.  This area will be closed to traffic during work hours Monday – Friday from 7AM – 5PM.  … Continued

Bungalow Avenue – construction at loop nearing completion!

Construction work on the Bungalow Ave loop is almost at the finish line!  The City’s contractor, Ghilotti Bros Inc. (GBI) began work on the final section of concrete work on April 27th, 2022.  The City has also entered into an agreement with Precision Concrete to shave offsets in the vehicular concrete, reducing hazards along the … Continued

Bungalow Avenue – PG&E gas line and sidewalk shaving

Construction work on the Bungalow Ave loop is getting closer to the finish line!  PG&E began their emergency gas-line work a few weeks ago and should be wrapped up by the end of this week.  The City’s contractor, Ghilotti Bros Inc. (GBI) will be returning to begin work on the final section of concrete work.  … Continued

PG&E gas line lowering – Bungalow Ave

A couple months ago during the City’s concrete replacement work on Bungalow Ave a shallow gas-line was hit.  The gas line was found less than 1 foot under the roadway surface.  Public Works engaged PG&E to address the issue by lowering the gas line.  Typical lead times for PG&E work are between 6 months to … Continued

Woodland Avenue project update

The paving of Woodland Ave that began on Tuesday, February 22nd, is now complete. Our contractor, Ghilotti Bros Inc., will be raising manholes along Woodland Ave through Friday, March 4th of next week. For this reason, there will be no parking along Woodland Ave. until they have finished.

Bungalow and Woodland Ave project

Project Engineer: JC Agcaoili Over the past couple of months Ghilotti Bros Inc. (GBI) has worked efficiently to remove and replace over 6,500 square feet of concrete road on the Bungalow Avenue Loop.  Both Public Works and GBI have also worked diligently to coordinate with residents in the neighborhood to minimize interruptions to garbage pick- … Continued

Bungalow and Woodland Ave: Project update 12-6-2021

Project Engineer: JC Agcaoili Work has begun on the concrete replacement taking place along the Bungalow Ave loop.  A large stretch of concrete along Bungalow from Picnic Ave to La Loma has already been removed, replaced, and reopened.   The eastern intersection of McCoy has also already been removed, replaced, and will be reopened at the … Continued

Bungalow and Woodland Ave project update

To minimize disruption to our local schools, paving along Woodland Ave is projected to take place over the Winter Break starting Dec. 20th.  Woodland Ave. Weather permitting, paving will begin that Monday and is expected to finish before the holidays that weekend.  In the same week, we also plan to pave the section of Bungalow Ave from Woodland Ave to Picnic Ave.  This section … Continued

Bungalow Ave and Woodland Ave project update

Project Engineer: JC Agcaoili Construction is continuing along on our Bungalow and Woodland Ave resurfacing project.  We’d like to thank everyone for your patience as we continue to place new, ADA compliant curb ramps along Woodland Ave.  The recent rains did present some challenges to our construction crews as they are having to clear out … Continued

Close window