Last week the City’s contractor Ghilotti Bros. Inc., was working on the installation of the retaining wall adjacent to the new bike facility on the West End. The contractor has also been working on the installation of fiber optic cable and conduit, pouring sidewalk, and the installation of American with Disabilities Act (ADA) improvements such … Continued
The City of San Rafael will be sending out weekly project updates with construction updates, traffic closure updates, and other relevant information for this project. To receive these updates, please sign up using the form at the left-hand side of the project website. THIS WEEK (August 22 – 26): Nightwork: Crews completed installing new water … Continued
The City of San Rafael will be sending out weekly project updates with construction updates, traffic closure updates, and other relevant information for this project. To receive these updates, please sign up using the form at the left-hand side of the project website. THIS WEEK (August 15 – 19): Nightwork: Crews trenched and installed new water … Continued
The City of San Rafael will be sending out weekly project updates with construction updates, traffic closure updates, and other relevant information for this project. To receive these updates, please sign up using the form at the left-hand side of the project website. THIS WEEK (August 8 – 12): Nightwork for water service connections completed … Continued
The City of San Rafael will be sending out weekly project updates with construction updates, traffic closure updates, and other relevant information for this project. To receive these updates, please sign up using the form at the left-hand side of the project website. THIS WEEK (August 1 – 5): Nightwork for water service connections continued … Continued
The City of San Rafael will be sending out weekly project updates with construction updates, traffic closure updates, and other relevant information for this project. To receive these updates, please sign up using the form at the left-hand side of the project website. THIS WEEK (July 25 – 29): Continued nightwork for the water main … Continued
The City of San Rafael will be sending out weekly project updates with construction updates, traffic closure updates, and other relevant information for this project. To receive these updates, please sign up using the form at the left-hand side of the project website. THIS WEEK (July 18 – 22): Nightwork for the water main replacement … Continued
The City of San Rafael will be sending out weekly project updates with construction updates, traffic closure updates, and other relevant information for this project. To receive these updates, please sign up using the form at the left-hand side of the project website. LAST WEEK (July 11 – 15): Nightwork for the water service connections … Continued
The City of San Rafael will be sending out weekly project updates with construction updates, traffic closure updates, and other relevant information for this project. To receive these updates, please sign up using the form at the left-hand side of the project website. LAST WEEK (July 5 – 8): Nightwork for the water service connections … Continued
The City of Rafael along with partner agencies Marin Municipal Water District, and the San Rafael Sanitation District’s Third Street Rehabilitation Project is well under way. The water main replacement west of Highway 101 is almost complete. The retaining wall necessary for the west end bicycle path connection is currently under construction. The City’s contractor … Continued