City Hall and other offices will be closed to the public from December 23 to January 3, but appointments are available upon request. Public safety and emergency services remain available 24/7.
As of October 14th, 2024, Bayo Vista Way and Terradillo Ave Easement have been completed. The following work is taking place on the following streets: Billou St.: The remaining lateral reconnections will be completed by October 25th, and paving will take place the last week of October. Madrona St: The sewer mainline installation and lateral … Continued
Project Update 8/21/24 The contractor plans to pothole and video existing sewer pipes on August 26th Replaced all seer main and lower laterals Grind and repave road on Miramar Ave and Miraflores Ave The contractor will abandon existing sewer main
Project Update 7/30/24 Replaced sewer main and lower laterals from 26 Miramar Ave uphill to Miraflores Avenue approximately 500 feet from 7/10-7/30/24. Installed new sewer main and extending existing sewer laterals on the eight feet lane easement. Installed new sewer manholes on Miramar Ave.
As of July 10th, 2024, Phase B1 is 95% complete. The properties that were previously connected to the corroded and inaccessible sewer mainline along the shore, were successfully connected to the sewer mainline on Oak Drive. Each property had an individual sewer pump system, and lateral installed on their property in order to connect to … Continued
Project Update Replaced sewer main and lower laterals on Miramar Ave starting at the intersection of 1st Street and Miramar Ave to approximately 450 feet uphill on Miramar Ave. Installed new sewer main and extending existing sewer laterals on the eight feet lane easement. The contractor is installing sewer main on Miramar Avenue between intersections … Continued
Project Update Replaced sewer main and lower laterals on Highland Ave starting at Jewell Street to approximately 400 feet east up Highland Ave. Replaced sewer main and lower sewer laterals on Spring Grove Ave between Greenfield Avenue and Terrace Avenue from September 30th to October 20th. Replacing sewer main and installing cleanout and backflow prevention … Continued
Project Update Replaced sewer main and lower laterals on Lindaro Ave and Woodland Ave The contractor replaces sewer main and sewer laterals on East St and Jessup St from October 2nd to October 20th.
Project Update Replacing sewer main and lower sewer laterals on Highland Ave starting at Jewell Street to approximately 400 ft East up Highland Avenue from September 30th to October 20th. Replacing sewer main and lower sewer laterals on Spring Grove Avenue between Greenfield Avenue and Terrace Avenue from September 30th to October 20th. Replacing sewer … Continued
Project Update Replacing sewer main and lower sewer laterals on Alexander Ave starting from W Crescent Dr including 78 to 40 Alexander Ave and the sewer pipes in sewer easement from 16 Alexander to 7 Alexander Ave from September 21st to October 6th. Replacing sewer main and lower sewer laterals on Glen Park Ave near … Continued