2025 Public Service Award Nominations are open! 

 

Category: Sanitation District

2023 Sewer Rehabilitation Project

Project Update 01/13/2025 SRSD  will be replacing  the sewer mainline and lower laterals on 5th Avenue from January 13th- 17th.  The construction crew will  working from Nye Street to 918 5th Avenue.  SRSD will be replacing the sewer mainline and lower laterals on Clyde and Belle Ave  from January 20th, 2025 to January 24, 2025.  … Continued

2023 Sewer Improvements- Various Locations

As of January 10th, the following locations have been completed: Madrona Street Billou Street Edgewood Way McCoy Road, 4th St and C St. Bayo Vista Way Terradillo Easement between  Marinita Ave and Terradillo Ave. 4th St. between Mary St and Grand Ave. The following work is scheduled to take place over the next month: West … Continued

2023 Sewer Improvements- Various Locations

As of October 14th, 2024, Bayo Vista Way and Terradillo Ave Easement have been completed. The following work is taking place on the following streets: Billou St.: The remaining lateral reconnections will be completed by October 25th, and paving will take place the last week of October. Madrona St: The sewer mainline installation and lateral … Continued

Miramar/Miraflores Marquard Sewer Project – 8-21-24

Project Update 8/21/24 The contractor plans to pothole and video existing sewer pipes on August 26th Replaced all seer main and lower laterals Grind and repave road on Miramar Ave and Miraflores Ave The contractor will abandon existing sewer main      

Miramar/Miraflores – 7-30-24

Project Update 7/30/24 Replaced sewer main and lower laterals from 26 Miramar Ave uphill to Miraflores Avenue approximately 500 feet from 7/10-7/30/24. Installed new sewer main and extending existing sewer laterals on the eight feet lane easement. Installed new sewer manholes on Miramar Ave.    

Bayside Acres Beach Sewer Relocation Project – Phase B1- Update

As of July 10th, 2024, Phase B1 is 95% complete. The properties that were previously connected to the corroded and inaccessible sewer mainline along the shore, were successfully connected to the sewer mainline on Oak Drive. Each property had an individual sewer pump system, and lateral  installed on their property in order to connect to … Continued

Miramar/Miraflores – Update

Project Update Replaced sewer main and lower laterals on Miramar Ave starting at the intersection of 1st Street and Miramar Ave to approximately 450 feet uphill on Miramar Ave. Installed new sewer main and extending existing sewer laterals on the eight feet lane easement. The contractor is installing sewer main on Miramar Avenue between intersections … Continued

2023 Sewer Pipe Burst – Update November 1

Project Update Replaced sewer main and lower laterals on Highland Ave starting at Jewell Street to approximately 400 feet east up Highland Ave. Replaced sewer main and lower sewer laterals on Spring Grove Ave between Greenfield Avenue and Terrace Avenue from September 30th to October 20th. Replacing sewer main and installing cleanout and backflow prevention … Continued

Close window