Category: SRSD Improvement Projects

2020 Sewer Replacement Phase 2 – Weekly Update February 21th

Project Update – Week of 2/20 WR Forde completed sanitary sewer main replacement on Marin St from Clayton Ave to Ross St. Sewer laterals on Marin from Clayton Ave to Ross St will be replaced and expected to be completed by February 24th. From 2/20 – 3/10, WR Forde will be on Clayton Ave and … Continued

Bayside Acres Phase B – Weekly Update February 9th

Project Update – Week of 2/9 WR Forde will be onsite Saturday 2/11 to CCTV the newly installed laterals completed late last year. This won’t impact traffic traveling through the area or any residents as the laterals were completed within the city and county right of way. In addition, the design team Nute Engineering has … Continued

Bayside Acres Phase A – Weekly Update December 5th

Project Update – Week of 12/05 WR Forde will be repaving the street along Point San Pedro and Main Dr. starting Thursday 12/8 until Friday 12/9. The eastbound section of PSP will be closed and traffic rerouted to the westbound road creating a single lane in either direction. All traffic should be prepared to slow … Continued

Bayside Acres Phase A – Weekly Update November 28th

Project Update – Week of 11/28 WR Forde won’t be onsite until Tuesday to address existing conditions along Main Dr. They’ll be situated on the hillside of Main Dr. for light trenching and backfill. Traffic control will be up along Main Dr. to allow for safe construction. The following week, WR Forde will be starting … Continued

Bayside Acres Phase A – Weekly Update November 21st

Project Update – Week of 11/21 WR Forde will be working along Point San Pedro for restoration of the curb. All residents should be aware while moving through the area and paying attention to the traffic flaggers stationed along the road. Speed limit is reduced to 25mph while they work. The following week, there will … Continued

Bayside Acres Phase A – Weekly Update October 31st

Project Update – Week of 10/31 WR Forde is continuing efforts to trench through the bottom half of Oak Dr. All residents can expect the lower section of Oak Dr. to be busy as they drive their excavator through the street. Flaggers will be monitoring the entry into Oak Dr. and directing traffic. Residents can … Continued

Bayside Acres Phase A – Weekly Update October 24th

Project Update – Week of 10/24 WR Forde has returned to the top of Oak Dr. to complete work on the manhole. This week they’ll have reduced construction presence along the street to allow for more residential traffic to flow. Two flaggers will be stationed at either side of Oak Dr. to direct all residents. … Continued

Bayside Acres Phase A – Weekly Update October 17th

Project Update – Week of 10/17 WR Forde is completing the work on Marine Dr. this week. They will still be using Marine Dr. as their main path of travel. Residents should continue to work with the onsite flaggers as they drive through the area. At the start of next week, WR Forde will return … Continued

Bayside Acres Phase A – Weekly Update October 10th

Project Update – Week of 10/10 WR Forde is fully focused on the Oak Dr. and Marine Dr. this week. Traffic along these residential roads will managed by their flaggers but do take caution as 16-wheeler trucks will be using Marine Dr. to make their turnabouts. The majority of main pipe and manholes will be … Continued

Bayside Acres Phase A – Weekly Update October 3rd

Project Update – Week of 10/3 WR Forde has made it the end of Point San Pedro Road with the last manhole base pour for the street on Thursday. The sequence for construction will require WR Forde to start installing the lower laterals and cleanouts to each property. They will continue working along Point San … Continued

Close window