The construction of the Public Safety Center continues to progress. The roofing on the building is completed and the interior walls have been insulated. The building is now weatherproof and is ready for the upcoming wet season. With an average daily crew of fifty workers, the contractor continues to hit critical milestones to keep the project on schedule. Just this week, the contractor received several vital materials and equipment, including elevators, doors, hardware, and bulletproof panels for the Police Department spaces. Having these components on-site will be instrumental in maintaining the flow of the project.
Fire Station 57 continues to move closer to completion with a fall grand opening in the works!