Updates to City Hall Hours on Fridays in July and August 

 

Fire Station 52 Update February 2018

Posted on March 26, 2018


Fire Station 52 February 2018 construction update

Project Progress

Alten Construction continues to work on the Fire Station and Classroom Buildings.  At the Fire Station Building, the CMU walls are going up along with electrical and plumbing rough in work.  At the Classroom Building, the Contractor continues their wood framing and electrical rough in.  The Contractor also completed the concrete work for the bio-retention walls on the site.

PROJECT TEAM:
Owner: City of San Rafael
Project/Construction Manager: Kitchell, Sacramento, CA
Architect: Mary McGrath Architects, Oakland, CA
Contractor – Alten Construction, Inc.

Download update here!

Back to Monthly Updates

Close window