Francisco Boulevard East at Grange Avenue Sewer & Storm Drain Repairs Project Progress

Posted on October 22, 2021


Bay Pacific Pipelines paving temporary asphalt sidewalk on Francisco Boulevard East

This project is within its last few weeks of construction by Bay Pacific Pipelines.  All the linear feet of sewer main pipe have been installed, as well as the lower laterals and all storm drain pipe near the Grange Avenue intersection.  Four of the properties along Francisco Boulevard East required some upper lateral work that the District took on as part of the overall rehabilitation of this section of sewer collection.  The severe pipe sag that this main sewer line had has been removed and this 960 linear feet section of pipe will function much better following this project.

Bay Pacific Pipelines expects to complete all work for this project by October 30, 2021.

 

Close window