Project Description: This project made necessary repairs and improvements on H Street between 5th Ave and Forbes Ave. Improvements included installation of a new storm drain system, ADA compliant wheelchair ramps, and resurfacing of the roadway. Additionally, the City’s project, in conjunction with the San Rafael Sanitation District, included installation of a new sanitary sewer line.
Project Status: This project is complete. Construction resumed on May 7, 2015 and was completed on August 24, 2015. H Street has been resurfaced and new pavement delineation has been installed from 4th Street to Forbes Avenue.
Project Contact: Leslie Blomquist, Department of Public Works, (415) 485-3355.