Miramar/Miraflores Marquard Sewer Project – 8-21-24

Posted on August 21, 2024


Paving

Project Update 8/21/24

The contractor plans to pothole and video existing sewer pipes on August 26th

Replaced all seer main and lower laterals

Grind and repave road on Miramar Ave and Miraflores Ave

The contractor will abandon existing sewer main

 

 

 