Coleman Childcare Center had issues with a sinking subfloor at the entrance. Due to deferred costs for larger projects, the flooring became costlier. As our team was removing the flooring, they found pests under the modular and pest control services were needed to remedy the issues. All damaged subfloor area was removed, and additional framing support added for new subfloor going in, linoleum was patched in. Pest control work...
Parkside Preschool had plumbing issues with their sink. The damaged sink plumbing was leaking from multiple connections, the faucet was worn and damaged beyond repair. The water damage to the surrounding area was significant. Our facilities team had to replace the sink basin, faucet, water shutoff valve, and removed and cleaned up the damaged area....
Albert J. Boro Community Center received a wiring upgrade for future computer stations. Our team added several new 120v electrical receptacles on walls as needed. While doing this upgrade, they also ran new wiring for the computers to have online capabilities. The team installed cat6 cable throughout the lab which will be concealed in walls to create a clean look...
The Pickleweed Childcare ADA ramp was in need of an upgrade. The ramp was slick and was creating a dangerous situation for the staff and children that use the facility. The team repainted the ramp with a non-slip paint and touched up the railings for a simple yet elegant solution to the problem!
Our facilities division provided the retaining wall behind City Hall with a much-needed paint job to keep our City Hall clean and well-maintained. It’s amazing what a pressure washer and a new coat of paint can do to brighten the area and enhance the public’s perception of the City
In December 2017, construction commenced for the Measure E-funded Public Safety Center (PSC), a new state-of-the-art facility for police headquarters and public safety services. On August 26, 2020, the City’s PSC achieved final completion. Due to the lengthy construction of the building and the increased demand from fire trucks and heavy vehicles stationed at the...
In a project managed by Junior Engineer Shawn Graf, the City’s contractor Ghilotti Bros., Inc. and their electric subcontractor, Columbia Electric, are replacing the traffic signal poles in the intersection for the new configuration of the crosswalks.
We are very excited to announce that the Public Safety Center Project has achieved substantial completion. On July 1st, the last items required to operate the facility were substantially completed by the contractor, Alten Construction. The surveillance cameras and building security, as well as the heating and air conditioning systems were commissioned and finalized. The...
Big thanks to our DPW facilities team led by Supervisor Omar Garcia, and his crew Michael Reiser and Anthoney Heaven for their hard work and positive, can-do attitude! The Public Safety Center Project is complete but miscellaneous additions continue to come up to make the building and its surroundings safe and 100% ready for occupancy....
Starting this month, Pubic Works Admin employees Erika Spencer (Administrative Assistant II) and Iman Kayani (Administrative Analyst) will be taking on new duties with other departments. Anne Derrick of Community Development will be retiring at the end of the month, and with the hiring freeze, a replacement won’t be made for some time. To assist...
Huge Thank you to Matt Von Bima and Trevor Thomas! These two have a combined work experience of over 20+ years working for the City of San Rafael. Recently, these two took on the task of painting seven (7) crosswalk intersections, stop legends, many directional arrows, and 22 bike lane symbols on Las Gallinas Ave –...
As our Facility staff were inspecting the Public Safety Center, they found two safety risks. They wanted to tackle these issues immediately before anyone got hurt! On the backside of the building, there was a 4 foot drop with no indication of elevation change. We installed temporary railing to ensure safety of our staff and...
The Sidewalk Repair Program, like most construction in the State stopped and took a pause in March and April. With the amendments to the Shelter in Place order allowing construction to resume, the City and contractor, Van Midde and Son concrete have slowly started repairing sidewalk again. Additional protective and preventative measures are being taken...
We are partnering with the San Rafael Chamber of Commerce and Downtown Business Improvement District to support our incredible business community as best as possible. Starting next week, the latest Marin County Public Health order will allow outdoor dining and retail based on the following guidelines: Guidelines for retail Guidelines for restaurants To facilitate outdoor dining...
With Shelter in Place, there has been a surge in illegal dumping around the City. Maintenance crews have been busy responding and notify adjacent property owners accordingly. The issue has been particularly worrisome as there are more people out than ever using sidewalks for their Shelter-in-Place walks – and they do not want to have...
The Shelter-in-Place order has been in effect for two months now. The State has issued a four-phase plan for counties and cities for businesses to reopen especially the ones that can operate outdoors like car washes, golf courses, constructions, etc. In San Rafael, the impact of the modified restrictions showed a slight increase in traffic. ...
The Parks Department completed vegetation management projects around the City this week. The areas included the sides of Oakwood and Maywood Drive in the Sun Valley neighborhood well as a stretch of medians out on Point San Pedro Road.
With the nicer weather and shelter in place, Paint & Sign crews have been able to catch up on some much-needed work on faded stops/crosswalks. With less traffic, it's easier to set up traffic control in various areas. Crews have also been able to stripe the roadways that have been faded including Biscayne, 3rd Street...
The construction team is working hard to meet the anticipated completion date. Interior finishes such as carpet, wall panels, whiteboards, and counter tops are currently being installed. Additionally, audiovisual, fire alerting, surveillance and other integral systems are being completed. In the next few weeks, we plan on finishing the site walls, brick stairs and planting....
Staff reported late last year on the funding by Transportation Authority of Marin to install a signalized crosswalk on Third Street in front of San Rafael High School. We are glad to report the design plans are at 95% complete and the project will soon be sent out for bids. The crosswalk will bring safety...
Public Works is making the necessary repairs to modular during the COVID-19 pandemic to ensure the safety of our city staff. Water damage in subfloor was detected under this window. All of the compromised areas were removed, replaced and made safe and solid. Exterior siding was removed and an area where water had penetrated was...
The Parks Department completed some much-needed work along the pathway behind Spinnaker IV. The crew focused on removing weeds and trash as well as pruning shrubs and reducing encampment sites.
To continue to slow the spread of COVID-19, the Marin County Health Officer has issued a new Shelter in Place Order (“Order”) that extends the shelter in place mandate through May 31, 2020 with some modifications. Under this new Order, small construction projects may continue if Construction Safety Protocols per Appendix B-1 of the Order...
Paint crews installed new stop signs at Martens Boulevard at Octavia Street. The streets division also changed the intersection at C Street and Taylor Street from a two-way stop to a four-way stop.
This week, the Streets paving crew took advantage of the Shelter-In-Place order to pave 3rd Street, that normally would have been congested with traffic. The Parks Division also got some much-needed vegetation maintenance done on Pt. San Pedro Road and Andersen Drive.
Over the last few weeks, we have been experiencing a massive influx of gang graffiti in San Rafael. The Public Works sign crew has been painting over the tags, but the walls get tagged again. These tags in the image below are located on Caltrans property under the freeway at Mission.
The COVID-19 Stay-in-Place order statewide has impacted many aspects of the way we conduct our daily activities especially outside of our homes. Limiting it made a significant influence in the way we conduct business whether it's personal or business. Traffic was impacted as many cannot travel or have no place to go except to procure...