On Monday, April 15th, the City Council approved seven temporary construction easements associated with renting private property. The project design continues to advance toward completion, which we anticipate by June 2019. The design team continues to coordinate with several private utility companies regarding the relocation of one wood utility pole as well as the installation...
The Falkirk Mansion is scheduled to get a new roof within the first few weeks of May. The badly needed roofing will replace the aged wood-shake shingles with a new fiberglass wood-shake-look shingle. Needing to keep within the fire code requirements, the fiberglass shingles were a good solution, and were carefully chosen based on their ...
Have you noticed the new parking lot signs around town? Streets Maintenance Crews received the first parking lot sign work order from Parking Services to install our beautiful new parking lot signs! The sign pictured is at the 3rd and Cijos Street lot. You may also notice the revamping of fresh paint in our handicap...
The Marin County Stormwater Pollution Prevention Program (MCSTOPPP) made up of Marin’s 11 cities and towns and the County of Marin recently received a nearly $700,000 grant to fund trash control infrastructure. MCSTOPPP was one of eight Bay Area communities that were selected by the EPA for funding. This is an important boost to local...
Over the last couple of weeks, the Contractor has made great progress on the bridge project by forming the approach ramps leading to each side of the pedestrian bridge. Additionally, the Contractor recently relocated parking lot lighting and a water line inside of the Toyota parking lot. Electrical work on the pedestrian bridge itself is...
Sustainable Sports Foundation will be hosting the eleventh annual Marin County Half Marathon event on Sunday, April 28 at McNears Beach. Starting at 7:30 a.m. until approximately 11 :30 a.m., Point San Pedro Road will be closed at the east entrance of Biscayne, through China Camp State Park. Access through China Camp will not be...
Synopsis: The NWS is predicting a fast-moving storm to hit the area today bringing about 1/3” of rain. Most of the precipitation is predicted to occur late this afternoon into the early evening. Dry, warming conditions are then expected to occur for the remainder of the week. It is entirely possible that spring has officially...
Despite the second wettest winter on record, the 2018 Sidewalk Repair reached the quarter way mark this week. With 7 more locations completed in the last two weeks, the program has now replaced sidewalks at 37 properties. Work continued in Gerstle Park as four locations on E St were successfully completed. With the rains tapering...
SAN RAFAEL, Calif. — As part of PG&E’s ongoing efforts to provide safe and reliable gas service to customers, contractors will perform routine gas meter inspections in Novato, San Rafael, Mill Valley, Sausalito and Tiburon this week. Contract workers are inspecting approximately 18,000 residential and commercial gas meters. The contractors with Underground Construction are carrying a...
Public Works and the San Rafael Sanitation District work around the clock to make sure that our infrastructure is functioning properly: our roads, traffic signals, sewers, bridges, City buildings, and more. Last week we opened our doors to City staff, residents and the community members of San Rafael for a behind-the-scenes look in to what...
With the help of Rob Carson, Program Administrator of the Marin County Stormwater Pollution Prevention Program, Public Works and Community Development met to learn about stormwater systems, and the rules and regulations that govern discharge to our creeks and bays. About 25 city employees attended the two-hour training at City Hall. The City, under a...
The basement at the PSC is looking more gorgeous each day. The concrete block walls have been installed allowing for plumbing, fire sprinkler piping and ductwork to be placed in the basement. Large pieces of equipment are being delivered and stored in the basement so that they are available as needed to expidite construction. A...
The City’s contractor, M3 Integrated Services, has installed the resilient rubber surfacing at the Albert Park play area. The landscapers were out this week starting some beautification improvements to the park. Once the final touches have been completed the City will be holding a ribbon cutting ceremony which is scheduled for April 29th at 3:30...
The City’s contractor Valentine Corp. resumed work last week. Due to the heavy rains the site was saturated with water and mud. Valentine Corp removed over 400 cubic yards of mud and installed spring drains that will divert several liters per minute out of the hill through a subterranean drainage system.
Cal Elite Builders poured the retaining wall for the new eletrical pad on Saturday. They have started compacting back-fill inside of the wall in preparation for pouring the new electrical pad. After this project is complete and new switch gear is installed the infrastructure at City Hall will be ready for solar panel installation on...
On Friday, March 15th, the City’s contractor hit a major milestone by installing the new pedestrian bridge over San Rafael canal. At 1:20 AM, a very large crane, stationed inside of the Toyota Marin parking lot, hoisted the bridge into place capping many years of planning and design. The installation of the bridge took a...
Alten Construction is currently installing the final touches to complete Fire Station 52. During the last few weeks Alten Construction has replaced the sidewalks, and curb and gutter. The landscaping, irrigation and planting to help enhance the project is already complete. The fire crews will be pleased to know that the bedroom furniture has been...
The Civic Center Dr. fire station is nearing completion too. The contractor has nearly finished taping and finishing the interior walls and painting has begun. Although, the site work has been impacted by the rain, the team projects to complete the concrete transformer pad to receive PG&E inspection in early April in time for PG&E...
Despite the continued on and off wet weather, Van Midde and Son Concrete and the City have been hard at work completing new sidewalk, curb and gutter. On Second Street alone, 2,000 sqft of sidewalk, 200 feet of curb and gutter, and a new storm drain were recently completed. With all the rain, the benefits...
The City of San Rafael will be accepting applications for the 2019 Sidewalk Repair Program beginning Tuesday April 2nd through Friday, May 17th. This will mark the second year of the City’s program aimed at assisting property owners with sidewalk, curb, and gutter repair. Residential property owners accepted into the program split the cost of sidewalk replacement (50-50)...
Over the past several weeks, our Public Works staff made presentations to the Pickleweed Advisory Board and Parks & Recreation Commission to discuss options for new playground structures at Pickleweed Park and to gather additional feedback from the community. The Pickleweed Advisory Board and the Parks & Recreation Commission were both pleased with the proposed...
If you've driven down Second Street this week - you may have noticed a lane closure along with some pretty major sidewalk construction between C and D Streets. Van Midde & Son Concrete began work on Monday with what might be one of the largest square footage of sidewalk repair in this year's program. The...
We should expect a drying and warming trend this week and into the coming weekend. YAY! The rain previously predicted for tomorrow is now expected to fizzle-out before it reaches the Bay area, so we’re expecting dry conditions for the whole week. Tides: Tide peaks for this week are predicted to range between 5.3-ft and 6.2-ft. With the predicted...
The Traffic Engineering Division got the go ahead from Caltrans to install an All Way STOP at Merrydale Road and US 101 South Ramps! The work includes: painting stop legends and limit lines, refreshing striping, and installing STOP signs and advanced warning signs. Our maintenance crews will do the installation in the wee hours of...
Over the last several weeks we have seen an extraordinary amount of rainfall pass through Marin County (see Rain, Rain Go Away article). Storm weather services have categorized some of the storms as atmospheric rivers”, a flashy name for a plume of tropical moisture in the atmosphere that can result in heavy rainfall or snowfall...
The North Francisco Pump Station was built by Caltrans in 1999. Its purpose is to pump large amounts of water from the surrounding area including the freeway, the Gerstle Park, and Bret Harte neighborhoods into the bay. There are 4, 250 horsepower (hp) motors and 2, 30 hp pumps, each 40 feet long, at this...
Dear March, we don’t want any trouble from you. February was a little iffy, so just come in, sit down, and don’t touch anything! Last week another major storm hit the Bay Area. Localized flooding due to rainfall and tides were recurrent but, our well-prepared City Maintenance crews worked through the evening and early morning...
Over the past few weeks Valentine Corp. has removed and replaced the concrete barrier on the east side of the Grand Ave vehicle bridge. The new pedestrian bridge arrived Friday morning (March 8th) in two pieces and is being stored inside of the Toyota Marin parking lot so that final assembly and installation of the...
The SMART Larkspur Extension construction work on the Francisco Blvd. West realignment and Phase-1 of the Multi-Use Path (from Rice Street to Andersen Drive) has been slowed a bit due to the rain. Ghilotti Brothers was able to squeeze-in one concrete pour for the MUP down at the Anderson Street connection. There are two small...
The Traffic Engineering Division is working hard to get our traffic signals modernized, starting with video detection. The cameras were installed at 4 locations (Mission/Hetherton, 2nd/Hetherton, 2nd/Irwin, 2nd/Grand). The images below are of 2nd Street/Irwin Street. The “MioVision” fish eye camera provides a live stream of the intersection; the second image shows the cars from...