On Monday December 17, 2018, the Federal Highway Administration (FHWA) approved the Federal Transportation Improvement Program (FTIP), which shows all of the proposed funding for projects throughout the region and state. The FTIP showed that the full construction funding for Southern Heights Bridge was approved for FY 18/19. The documents note $4,185,000 for construction. Public...
With the help of Parisi Transportation Consulting, Public Works was successful in applying for, and receiving grant funding from the Federal Highway Safety Improvement Program (HSIP) for 3rd Street from Lindaro Street to Grand Avenue. The $1,575,000 will fund high-visibility crosswalks with accessible curb ramps, advanced stop bars, pedestrian countdown signals at five intersections and...
In early December, the contractor completed installation of the bridge abutments on each side of the San Rafael Canal. With abutment work complete, the contractor is focused on replacing the bridge barrier located on the west side of the vehicle bridge. While on the surface this barrier may appear simple to install, the barrier requires...
The City’s contractor Valentine Corporation poured the first concrete wall and is in the process of stripping the forms and backfilling behind the wall. The contractor will rebuild the slope up to Irwin Street and start working on the last retaining wall during the holidays. After the 4th retaining wall is finished the contractor will...
On December 17, 2018 the City Council authorized a contract with a local engineering design firm to develop a design to add a double right turn lane onto east bound 2nd Street from the North Bound 101 off-ramp to central San Rafael. The design is being fast tracked with the intent to include this work...
Construction at the following four addresses is anticipated to begin January 3, weather dependent: 26 Eye Street 40 Harcourt Street 149 Forbes Ave 135 H Street Construction on average is anticipated to take up to 5 days, starting with demolition of the existing sidewalk, removal of minor tree roots, followed by placement of the forms...
Link to full Parkette Routine Landscape Maintenance Request for Proposals (RFP) The City of San Rafael (City) hereby requests proposals for routine landscape maintenance. It is the intent of the City to hire a fully-licensed landscaping contractor that is duly registered and licensed with either a C61 or C27 license in the State of California. Services...
Construction has started at the 6 initial Sun Valley properties identified in the 12/4/18 – Sidewalk Repair Program (SRP) Update. Today Van Midde & Son Concrete crews demoed out over 700 square feet of sidewalk, and will getting ready to set forms for the new concrete as soon as tomorrow or Wednesday. The new sidewalk...
No rain the immediate area is expected until late afternoon Thursday. But it’s not expected to produce very much precipitation. Then there should be another break until late Saturday night with more light rain expected. The King-tide season is upon us as peaks at the Golden Gate Bridge are predicted to reach 6.9-ft by Sunday...
Last week our Parks Maintenance visited the 32 Sidewalk Repair Program locations where trees have been identified as needing removal. The majority of these locations were trees in the Right of Way (located between the sidewalk and the street) but five of the properties involved trees on private property. See diagram below: As a reminder,...
Weekly Synopsis The NWS predicts chances of isolated showers north of Santa Cruz today and tomorrow with a drying trend into Wednesday. However, for the San Rafael area there isn’t much rain predicted until late Friday when a front moves through the area. Then, we may expect a wet weekend containing light showers. Peak tides...
Thanksgiving weekend brought the City of San Rafael its first good storm of 2018 with 3.5 inches of rain over a 3-day period. Public Works crews performed an on-site emergency pump repair at Kerner Pump in-between Storms. The Streets pump crew removed, repaired and reinstalled the pump within a five-hour period. Just in time for...
During mid-November, the contractor installed 27’ deep pile foundations on each side of the San Rafael Canal. While the pounding of concrete generated a lot of noise, the work was done in about 12 working hours split up over three days. The next step is for the contractor to construct the bridge abutments on top...
With a lot of large projects happening in our hustling and bustling downtown, the folks in the Traffic Engineering and Land Development Division are working hard to continue coordinating with all the general contractors, subconsultants, and agencies that have their hands in everything from water to sewer to sidewalk repair to pavement restoration. Our inspectors...
The SMART Larkspur Extension construction work on the Francisco Blvd. West realignment and Phase-1 of the Multi-Use Path (from Rice Street to Andersen Drive) continues to move forward with the bulk of the work at the new Rice Drive and Francisco Blvd West intersection and rail crossing. Underground drainage facilities and preliminary grading have been...
It’s been busy at the Public Safety Center site! In the last three weeks, the contractor had two extremely successful concrete pours. A total of over 1,000 cubic yards of concrete was placed by crews of up to 50 workers including truck drivers, concrete pump operators, concrete installers, finishers, and the construction management team. This...
The City’s contractor, M3 Integrated Services, has been working on grading the hillside and installing the underground utilities. This project will continue through the winter. The contractor has been winterizing the site before every rain.
The City’s contractor, McNabb Construction, has demolished the existing Arbor at Bret Harte Park and intends to begin trenching for the sewer line once the weather clears up. The shade structure should be installed by the end of the year and the long-awaited restroom should be placed and completed by the end of January.
The City’s contractor, Hillside Drilling, has completed the retaining wall and has placed erosion control measures. They should be 100% complete with the slide repair by the end of the year.
The City’s contractor, Valentine Corporation, has completed the first two retaining walls and is now forming the first cast in drilled hole (CIDH) retaining wall on the slope. They have also started demolition of Gleniare Drive in hopes of completing the lower phase of the project before the end of the year.
Construction at the following six addresses is anticipated to begin December 17, weather dependent: 102 Eye Street 110 Center Street 132 Center Street 27 Harcourt St 3 Pine Street 30 Center Street Van Midde and Son Concrete will email property owners a few days prior to commencement of work. Construction on average is anticipated to...
Weekly Synopsis Dry and seasonably cool weather is forecast through this afternoon. Unsettled weather conditions return late tonight into Tuesday as a storm system approaches the central California coast. This is a lighter storm with a predicted total of about 0.65” Monday-Tuesday and then about a 0.25” Wednesday-Thursday. Dry conditions are expected to return by...
Today at the San Rafael Transit Center, Sonoma-Marin Area Rail Transit (SMART) construction begins in preparation for SMART's rail extension to Larkspur. Transit users can now see construction fencing and staging areas within the Transit Center. Work will progress over the coming weeks and include the construction of a new temporary boarding platform near Platform C at...
As of 11/29, the City has received signed agreements from 183 property owners in San Rafael for sidewalk construction work. We are excited that the first year of the program will be making a visible impact on sidewalks in San Rafael, with 22,453 square feet of sidewalk slated to be replaced, representing over a mile of new sidewalk...
On Thursday, November 29, 2018 our contractor for the Grand Avenue Pedestrian Bridge project is planning on installing temporary K-rail (a concrete barrier used to separate or redirect traffic) on the existing bridge. The contractor will have flaggers and signage for traffic control while the K-rail is being placed. Work begins at 9:00 pm and...
The City has hired BkF Engineering to assist in attaining the ROW Certifications, final project planning and assistance with the construction process. The ROW Certification process is underway and is expected to be completed late this summer. Then, construction is planned to start up mid-December 2019 and be completed by November 2020. When completed, the...
*UPDATE* All open space areas in the City of San Rafael have been reopened as of Friday, December 7 due to low fire danger. All open space areas in the City of San Rafael are closed to the public until further notice due to extreme fire danger. Per San Rafael Municipal Code 19.10.040 Due to...
The Air District is issuing a smoke advisory today due to the Butte County fire that developed a week ago. Heavy smoke from this wildfire in the North Bay counties is causing very unhealthy air quality throughout the region and is not expected to improve for several days. . Bay Area residents impacted by wildfire smoke are advised to: Limit outdoor...
As of 11/8/2018, Van Midde and Son Concrete has submitted proposals to all participating property owners. That includes some 200 proposals of which the City has received 157 signed and returned from the property owner. The City will be sending reminders to the remaining 43 property owners that they have until November 26th to return their signed proposals....