The SMART Larkspur extension construction realignment of Francisco Blvd. West and first phase of the Multi-Use Path (from Rice Street to Andersen Drive) continues to move forward at a rapid pace. The Contractor has nearly completed the curb & gutter and sidewalk installation for the new Francisco Blvd West. The sheet piles that support the...
Van Midde Concrete has conducted 114 of 198 final inspections and will be sending out all remaining final agreements for property owners to sign over the next few weeks. Property owners are instructed to sign the final agreement from Van Midde, and send the City a copy. Once the City receives the copy of the...
The construction team continues to show results at our Essential Facilities projects. At Fire Station #52, with the training tower complete, the contractor has refocused its resources for the interior build out of the main building, exterior facade, and the on-site and off-site utilities. Bay Cities Paving & Grading, a subcontractor to Alten, will continue to...
Over the last several months PG&E has been working on a vital natural gas main that travels through the Bret Harte neighborhood and feeds most of southern Marin. After the San Bruno pipeline explosion, PG&E thoroughly evaluated gas lines throughout the state and identified this one as one needing replacing – as the system has...
Progress on the SMART Larkspur extension construction continues to move rapidly with the Francisco Blvd. West realignment and Phase-1 of the Multi-Use Path (from Rice Street to Andersen Drive). The Contractor has placed the aggregate base and is now installing curb & gutter on the north end. Construction of the Multi Use Path-Phase 1 is...
Public Works and contractors have been hard at work answering sidewalk repair inquiries and final inspection scheduling all throughout late July and August. Thank you to all applicants that have arranged for the final inspection required with their preferred contractor before the deadline. Do not be alarmed if contractors are slow to respond, doubling of...
DPW has started its annual review and repair of several storm water pumps. This year we are removing a total of three pumps for repair or possible replacement. In order to review and determine if the unit need repair, the entire pump is removed and shipped to the contractor’s yard where it is dismantled and...
The SMART Larkspur extension construction work continues with the Francisco Blvd. West realignment and Phase-1 of the Multi-Use Path (from Rice Street to Andersen Drive). The Francisco Blvd West realignment is moving forward at a fast pace. The subcontractor, Ghilotti Brothers Construction, is not wasting any time with construction. The work includes environmental mitigation of...
In early August Public Works staff reported that a portion of Francisco Blvd. West and Andersen Drive was scheduled to be resurfaced starting on August 9, 2018. The approach included grinding the roadway on Friday night and performing the resurfacing on Monday night. SMART’s contractor was required to secure an encroachment permit from Caltrans the...
City Staff from the Community Development Department and the Public Works Department met with representatives from the San Rafael City School District last week to discuss the construction work occurring on various school campuses. Glenwood Elementary School: The school district is started construction of a new gym and multi-purpose rooms on the campus. Construction started...
On Monday, August 20th, the City’s contractor, Ghilotti Bros, began construction at the intersection of 5th/G Street. The first order of work includes removing an old storm drain culvert dating back to 1928. The Contractor removed the pipe and installed a new storm drain pipe across the east leg of the intersection. Over the next...
Last year as part of a larger effort to improve pedestrian safety, the City developed an evaluation and prioritization process to score and rank uncontrolled pedestrian crossings. An uncontrolled pedestrian crossing is where the sidewalks or designated walkways intersect a roadway at a location where there is no traffic control (i.e. traffic signal, STOP sign). ...
On August 16, 2018, the Ghilotti Bros. ground and paved (using 80 tons of hot mix asphalt) the end of Clayton Street which had deteriorated beyond a less intensive treatment. This is small piece of road heavily impacted the residents in the neighboring area. After voicing their opinions about the dilapidated asphalt, DPW was able...
DPW’s four man Sign and Paint Crew gave Second and Third Street intersections, from the Miracle Mile to Lincoln Ave., some fresh paint to brighten up the directional arrows and lane lines. Two streets down, 1067 to go!
On Friday night, August 9, 2018, SMART’s contractor will be grinding the asphalt at the intersection of Andersen Drive and Francisco Blvd. West. Traffic control measures will be installed at 7:00 pm and the intersection will be closed at 9:00 pm to get started. Traffic controls will be in place to direct the public around...
The SMART Larkspur extension is at full speed ahead with the Francisco Blvd. West realignment and Phase-1 of the Multi-Use Path (from Rice Street to Andersen Drive). SMART’s contractor, Stacy Witbeck/Herzog has completed installation of the underground drainage and is now grading for the realignment of Francisco Blvd West and the SMART tracks between 2nd...
Public Works crews from the Street Division have begun removing accumulated sediment and cattails from the City of San Rafael drainage channels. Our crews clearing about 4 miles and 900 tons of material from City of San Rafael drainage channels. We will be clearing the channels along the 580 Highway and Manuel T. Freitas Parkway. ...
We are thrilled to see the construction teams make huge progress at all three Essential Facilities projects. At Fire Station #52, the Training Tower erection has been completed. Minor electrical and mechanical work is to follow and is scheduled to be completed by the end of August. The Training Classroom is now completely watertight and...
Following concerns brought up by City staff during the monthly Health and Safety Committee meeting, the Department of Public Works was asked to have the seat wall behind Safeway on A street removed due to the threat to public health and safety. This week the Ghilotti Bros. removed the wall and restored the area. The...
The intersection at Andersen Drive and Francisco Boulevard West will be closed each night from 7:30 pm to 6:00 am starting August 10, 2018 through August 13, 2018. The span of the closure will be from Francisco West (O’Reilly auto parts driveway) to Andersen Drive. The work being done to the intersection will consist of...
Proposal Post Date: July 26, 2018 Proposal Due Due: August 21, 2018, 10:00 am (see Addendum #1) Link to full FY 2018-19 Routine Tree Services Request for Proposals Document Addendum #1 The City of San Rafael (City) hereby requests proposals for on-call tree services from a qualified tree maintenance business that is duly registered and...
Proposal Post Date: July 26, 2018 Proposal Due Due: August 21, 2018, 10:00 am (see Addendum #1) Link to full FY 2018-19 Emergency On-Call Tree Services Request for Proposals Document Addendum #1 The City of San Rafael (City) hereby requests proposals for on-call tree services from a qualified tree maintenance business that is duly registered...
On Monday, July 16th City Council approved a $4.50 annual increase for the Pt. San Pedro Median Assessment District – the first increase since the inception of the Assessment District in 2013. For the last few years, the revenue generated for the Operations and Maintenance of the district has not covered the actual operations and...
Freitas Parkway The Parks Department finished their annual pruning of the medians on Freitas Parkway last Saturday. This is the largest pruning project the department undertakes each year and took a total of 10 full work days to complete. Twenty-five truckloads of material were cut and cleared from the medians. There will be a channel...
SMART’s contractors have hit the ground running on the Francisco West roadway improvements between Rice Dr and Second St. The old roadway has been completely removed, and the contractor is diligently working on the underground work. To date, lengthy sections of new storm drain pipe have been installed. Rice Dr remains open as a detour...
In anticipation of the new time-limited parking changes coming to East San Rafael, the City recently sent over 4,000 letters to residents, businesses, and property owners in the area. Public Works spent the past few weeks marking locations of poles that will be installed to hang the new signs associated with the parking changes. These...
On Monday evening, Lauren Davini, Traffic Engineer, brought the San Rafael Bicycle and Pedestrian Master Plan 2018 Update to City Council, where they approved the Plan and the Negative Declaration unanimously. Updating a Bicycle and Pedestrian Master Plan is no easy task; it was a year and a half of gathering and mapping existing conditions,...
Pre-construction inspections were completed on June 18th. Staff is now working on finalizing the data for inspections of the 366 private properties that applied for the Sidewalk Repair Program. Depending on the work required, some homeowners may see white spray paint on their sidewalks. Due to the Fourth of July holiday week, and double the...
Point San Pedro Road Streets Maintenance crews spent some time on Point San Pedro Road (PSP) at Loch Lomond Drive extending the existing red curb on PSP from 20ft to 80ft. In addition, the shoulder lane was changed to 100ft of “skips” markings leading up to Loch Lomond Drive for bicyclists. Las Flores at Las...
A grand opening ceremony was held on July 2, 2018 at Victor Jones Park to celebrate the installation of the two new play structures. The 2-acre park, which is located off of Robinhood Drive in the Glenwood neighborhood, was originally built in the late 1970s and utilized older play structures and facilities. The construction project...