At Monday’s meeting, the City Council will also consider two budgetary matters: the Three-Year Capital Improvement Program (CIP) and the Measure A - Open Space Work Plan. These two items will be incorporated into the City’s Fiscal Year Budget as part of the budget process next month. The CIP is the long-range plan for all...
Project Update During the month of April, Alten Construction completed the installation of under-slab rough electrical and plumbing elements, and also completed the placement of underslab rock and vapor barrier at the Living Quarters. CMU installation continued at the Apparatus Bay and Utility Rooms. Selected steel elements (ledgers and columns) and steel door frames were...
Project Update During the month of April, Alten Construction continued work on the Fire Station Building, the Training Classroom and the Training Tower. The Training Tower foundation slab on grade was placed mid-April. The Tower structure design submittal was approved and in early May the Tower erectors will be on site to begin erection. The...
During the month of April 2018, the weather cleared up allowing Alten to initiate the off haul of the clean material, contaminated material and prepare the building pads for certification. Hauling off of the clean material was a success hauling off approximately 2,500 cubic yards to the airport. During the excavation of the contaminated material...
The City of San Rafael (City) hereby requests proposals from qualified Consultants for the project management and oversight of Automated Traffic Signal Measures (ATSPM) and Adaptive Traffic Control Systems (ATCS) Projects. The final product sought is a completed and successful ATSPM implementation meeting all Innovative Deployment of Enhanced Arterials (IDEA) grant funding contract requirements provided...
The Sidewalk Repair Program application period closed on Friday, April 27th. The City received 366 in total applications. This week the City ran the Sidewalk Repair Program lottery and ranked all 366 applications, and sent an email to all applicants informing them of their priority ranking status and what the next steps are: 1 is...
We had our first two Park-A-Month volunteer days on April 21st (Gerstle Park) and May 5th (Sun Valley Park). Both events had a good turnout, with 30 volunteers showing up at Gerstle Park and nearly 50 at Sun Valley. Many saw the event on NextDoor, signs in the neighborhood and volunteer postings on the website....
SMART’s contracting team continues to make progress on Andersen Dr. A team of contractors are simultaneously working to install portions of the multi-use pathway near the railroad crossing, traffic signal infrastructure, and earthwork preparatory to the new railroad tracks being installed. The contracting team is diligently scheduling the phasing of work at the intersection of...
Bike to Work Week encourages commuters and others to get out of their car and use a bicycle to get to and from their work. Safe paths for bicyclists are essential to make riding a real possibility for commuters. The City will conduct a one week pilot project from May 7 to 11 to coincide with Bike...
Also on Monday evening, the City Council will consider using $850,000 in granted bike path funds to purchase steel components to be used to build the multi-use path that will parallel the SMART Larkspur Extension rail line at its crossing near Francisco Boulevard West. The multi-use path will provide a dedicated space for pedestrians, bicyclists,...
Project Update: During the month of March, Alten Construction mobilized material and equipment and began installation of CMU at the perimeter and interior building walls. The installation of UG MEP elements (including deep interior and Apparatus Bay trough drain aspects) was completed. Delivery, staging, and set up of CMU material and equipment continued during the...
Project Update: During the month of March, Alten Construction continued work on the Fire Station Building and the Training Classroom. The Training Tower foundation work initiated with anchor pier delivery, installation and successful pull-testing. Tower footing rebar installation was ongoing at the end of the period. At the Fire Station Building, the CMU block was...
During the month of March, the weather turned for the worst raining constantly pushing the site to its limits forcing the team to act quickly. An additional baker tanks was brought to the site and the purchase of pumps was required to help contain the rain water on site. The pumps had to be placed...
Bike to Work Week encourages commuters and others to get out of their car and use a bicycle to get to and from their work. Safe paths for bicyclists are essential to make riding a real possibility for commuters. The City will conduct a one week pilot project from May 7 to 11 to coincide with Bike...
The City of San Rafael (City) hereby requests proposals from qualified consultants for the design of a rehabilitation of an existing bathroom located at the Jean and John Starkweather Shoreline Park. The final product sought is construction contract documents including cost-effective design options, plans, specifications, and cost estimates ready for bid. Proposals shall be submitted...
We’re always looking for ways to make San Rafael more bike-friendly. On Monday night, the City Council will hear about a pilot project to create a “cycle track” on Tamalpais Avenue during Bike to Work Week, May 7 to 11. During that week, we will convert Tamalpais Avenue to a one-way street and create a...
Also on Monday evening, the City Council will consider awarding a $1.5 million street resurfacing contract to Team Ghilotti and a $100K agreement with Park Engineering for associated inspection services. The staff report outlines which streets will be repaved. Additional neighborhood outreach will be conducted closer to the time of the projects. Read the staff...
Help the City of San Rafael and the Marin County Stormwater Pollution Prevention Program (MCSTOPPP) understand pollution prevention practices by filling out this short survey! Your survey will help MCSTOPPP decide how to direct outreach and education resources to have the biggest impact to prevent pollution from getting into our creeks and the Bay. Thanks...
Project Description: These two projects include installation of hot mix asphalt and/or micro-surfacing treatments at various locations throughout the City. This project also includes installation of American’s With Disability Act (ADA) compliant curb ramps, curb, gutter, and sidewalk. Curb ramps must be installed prior to resurfacing of streets per federal law. Project Status: Below is a list of roads that will potentially be...
The existing taxi station at the Transit Center will be closed due to construction at the Transit Center beginning February 5 for the SMART rail extension to Larkspur. Taxicab operators expressed concerns at the most recent City Council meeting that without a new cab stand in place, the transit using public and city streets would...
In early January Andersen Drive was closed temporarily as SMART performed rail welding work along the rail line. Starting February 26, the Andersen Drive closure will be reinstated, 24-7 for an estimated three months. SMART will be constructing the actual rail crossing across Andersen Drive and utilities will be performing important work relocating several key...
Due to construction and the upcoming SMART connection to Larkspur, the taxis that are ordinarily staged within the Bettini Transportation Center need to be relocated. On Monday evening, the City Council will consider establishing a new taxi stand at Tamalpais Avenue East, between Third and Fourth Streets. Tamalpais East is a one-way street that currently...
This morning, December 28, 2017, the City received notice from Caltrans bridge inspection staff that the existing Southern Heights Bridge should be closed effective immediately due to structural safety concerns. As a result, we've closed the bridge and installed detour signage. The City is currently working with a bridge consultant to design a new concrete...
The City takes a big step this week in its commitment to increase energy efficiency and reduce San Rafael’s overall carbon footprint with the replacement of more than 2,700 street light bulbs with LED lights. The LED (light-emitting diode) lights, use dramatically less energy than standard older, high pressure sodium lights, and are estimated to...
As you likely know, the SMART rail line bisects the existing Bettini Transit Center in Downtown San Rafael owned by the Golden Gate Bridge, Highway, and Transportation District. As SMART is currently underway with their construction of their extension to Larkspur, modifications will be made to the existing transit center so that bus service can...
Over the past few weeks, the contractor has made great strides to complete the wheelchair ramps and sidewalk, with only one small portion remaining. The landscaping contractor has installed an irrigation system for future use, and will install mulch throughout the landscape areas. On November 7th, the electrician began erection of the new traffic signal...
Many people in our community were touched by the late Public Works Director Dean Allison. He was not only an incredible public servant, but also a dear friend. After his passing, the City created the Dean Allison Internship. The first recipient, Thomas Wong, wrote this moving piece about spending a day with Dean and the...
Did you know there are over 275 miles of sidewalk in San Rafael? After significant work with neighborhoods and property owners, the City Council will consider a sidewalk maintenance and liability ordinance at their meeting on Monday evening, at 7 p.m. The proposed program clarifies the responsibility for performing and funding maintenance as well as...
SMART has already started performing work on the Larkspur extension. They have been installing sheet pile and constructing improvements along the new rail line. Next week SMART’s contractor will be closing Francisco Blvd West on October 17-24 to remove the existing wood trellis and wood walls along the San Rafael creek. Since these existing facilities are...
"Seeing his legacy not just at Public Works but throughout the City of San Rafael inspires me to continue learning, growing, and making a difference in the community." - Former Dean Allison Intern Thomas Wong, former Dean Allison Intern, was recently featured in a Marin Independent Journal story about his experience. Also, read his personal...