The City of San Rafael is replacing the Peacock Gap Park play equipment and improving pathways in the area.
Construction is scheduled to begin on February 24, 2025 and be completed in July. Work hours will be 8am-5pm, Monday-Friday.
Project goals
- Replace aging playground structures
- Improve accessibility of the path of travel to the playground
Budget
Planning/Design | $130,000 |
Construction | $925,000: Measure A Funds |
Overview
Peacock Gap Park is a popular community park in the City. It offers playgrounds, shaded bench areas, two tennis courts, playing field, and walking trails.
The Library and Recreation Department allocated measure A funds to replace the existing play structures and improve accessibility around the park. The City has engaged a consultant to facilitate design, and will later advertise the project to solicit bids from contractors to construct.
Community Input
The City hosted an outreach event on Saturday, June 22nd at Peacock Gap Park to collect feedback on the design of the park. Additionally, a community survey was published online June 15-July 1, 2024 to gather feedback. Hundreds of participants shared their ideas!
You can view the initial design alternatives we asked for feedback on and the final project documents below.
Final Drawings – Peacock Gap Park
Timeline
Collect topographic survey and prepare preliminary design options (complete) | March 2024 – June 2024 |
Public meeting and online survey (complete) | June 2024 |
Recommended design presented to the Park & Recreation Commission | August 8, 2024 |
Advertise project to solicit bids | Late Summer 2024 |
City Council Awards Contract | Fall 2024 |
Project Start | February 2025 |
Goal for project completion | July 2025 |