Apply to serve on a San Rafael Board, Commission or Committee!

   

What is the overall cost of the project? Where are grant funds being received from and when do they expire? Are there alternative funds available if the project costs increase?

The current estimated cost for the project is $4 million. This includes construction, inspection services, and outreach efforts during construction.

 

The project has been awarded funds from the One Bay Area Grant Cycle 3 (OBAG 3) for the construction of the project. OBAG 3 funds must be obligated by January 2027 and fully expended by January 2030 (36 months after construction award).

 

The City will update the estimated cost for the project as part of the 95% Design effort. The City will inspect any potential funding shortfalls at this time and look for alternative funds if needed.

Close window