Construction Start: April 2023
Estimated Completion: Fall 2024
Work on the San Quentin Pump Station Reconstruction project continues with the wet well and pressure vault of the new pump station. As shown in the pictures, the formwork for the wet well and pressure vault was constructed, allowing for the pouring of concrete. Work in August will continue to be focused on completing the concrete structure, particularly focusing on the portion above the recently poured walls. PG&E is expected to relocate their pole that is near the construction site on July 20th.