Project Update 8/21/24 The contractor plans to pothole and video existing sewer pipes on August 26th Replaced all seer main and lower laterals Grind and repave road on Miramar Ave and Miraflores Ave The contractor will abandon existing sewer main
Project Update 7/30/24 Replaced sewer main and lower laterals from 26 Miramar Ave uphill to Miraflores Avenue approximately 500 feet from 7/10-7/30/24. Installed new sewer main and extending existing sewer laterals on the eight feet lane easement. Installed new sewer manholes on Miramar Ave.
As of July 10th, 2024, Phase B1 is 95% complete. The properties that were previously connected to the corroded and inaccessible sewer mainline along the shore, were successfully connected to the sewer mainline on Oak Drive. Each property had an individual sewer pump system, and lateral installed on their property in order to connect to...