Search Results

Filters

8123 Results Found

DPW maintenance worker Matt Gaehwiler, along with a contracted labor crew, cleaned areas underneath the Highway 101 viaduct. This area has been littered with trash and debris the past couple months due to homeless residents that have vacated the area. SRPD received a consent letter from CalTrans to enter their property and clean up the...

North San Pedro Road between Merrydale Road and the SMART Railroad crossing recently received fresh striping. The centerline and lane lines were restriped, and a striped island was added to further separate the two directions of travel. The City is working with SMART to review this area for additional improvements.    

As part of an ongoing collaboration between the City, SMART, and CPUC, the city reviews upcoming projects to see how they can enhance safety at railroad crossings adjacent to these city projects. This week as part of the Francisco Blvd West one-way conversion project, the city’s contractor installed warning striping on 2nd Street between the...

The City had two important kick-off meetings with the US Army Corps of Engineers (USACE) staff on November 5th and 12th. The first was a virtual introduction to the project team at USACE that will be working directly on the San Rafael Channel dredging environmental/design, and the second was an in-person site visit to the...

Whether a resident is insured or not, local options for testing are available Marin County residents seeking COVID-19 testing have more options than ever. Every day, an average of more than 1,000 Marin residents are tested for the disease, and residents should be aware of their options as case counts rise. Because navigating new choices can be challenging, an updated...

The Transportation Authority of Marin (TAM) has kicked-off a study of the feasibility and potential benefits of allowing buses to bypass heavy traffic on the US 101 by using the existing shoulder from Atherton Avenue/San Marin Drive in Novato to Mission Avenue in San Rafael. When buses can bypass congestion, transit (and sometimes even private...

That is correct. The sediment quality approval process under the umbrella permit would take advantage of a testing exemption allowed for in the EPA guidelines that allows for a report to filed referencing the USACE testing results. This exemption report is included in the umbrella permit cost. However, if USACE finds contamination in the main...

Permit acquisition would not be affected by any detected contamination, but the sediment quality approval required by the permits would be. Yes, any homeowners near areas in the main channel that the USACE testing shows to be contaminated would be responsible for additional testing near the dock that would hopefully show the contamination does not...

The City wanted to start the permit process now so that dock owners would be cleared to dredge when the USACE started. The FY2021 Work Plan began on Oct. 1. It is still not clear whether they will have funding available after the Work Plan’s priority projects (i.e. Oakland and Richmond Harbors) are completed. If...

The USACE pulls their own permits, but will rely on a consultant for their sediment quality approval. They have not selected that consultant yet.

Yes. The City is working with the USACE so that the dock owners can “piggyback” on the main channel project using the same contractor that the USACE uses, which will result in both scale savings and savings associated with the elimination of mobilization cost.

The City is working with the USACE so that the dock owners can “piggyback” on the main channel project using the same contractor that the USACE uses, which will result in both scale savings and savings associated with the elimination of mobilization cost.

There is a pro in this approach if a HOA or property owner wants to undertake the dredging on their own without piggybacking on the Corps dredging of the federal channel with the other dock owners on the Canal. If a dredging contractor was doing your dredging independently, they would probably do the permitting at...

The umbrella permitting cost will be dependent on the number of dredgees. The permitting process will include the acquisition of all permits PLUS the sediment quality approval. The future umbrella DREDGE CONTRACTOR cost will be based on the amount of dredge material and will be split between between all permitted dredgees.

Last week, based on an increased number of positive cases in a short time frame, Bay Area health officers made the decision to tighten local restrictions to mitigate the spread of COVID-19. The motivation was to get ahead of a surge and a possible state mandate to move back into Tier 2 (Red/Substantial). However, despite this attempt, the State announced that Marin, along with eight other counties, would be moving back...

Street Leaf Sweeping Will occur on November 21, 2020 starting at 7:30 AM. Public Works crews will be sweeping the following areas: Gerstle Park Additionally, Public Works will sweep up as many side streets as time permits.

Starting November 23rd through November 25th, City Hall and most non-essential City facilities, which include Public Works, will be closed in accordance with the non-public safety Furlough Schedule, which is a cost-saving measure in response to significant COVID-19 related revenue losses the City continues to experience. The 13-day closure schedule, as approved by our City...

Close window