Homelessness Update Community Meeting, October 3, 2024, via Zoom; click here for more information.

Search Results

Filters

8124 Results Found

Background Grand Avenue and Francisco Boulevard East form the primary corridor for residents living in the Canal Neighborhood, the most densely populated area in Marin County, to access the San Rafael Transit Center, SMART station, Montecito Plaza, and San Rafael High School. Local street connections between the Canal Neighborhood and the rest of the City...

As of 11/8/2018, Van Midde and Son Concrete has submitted proposals to all participating property owners. That includes some 200 proposals of which the City has received 157 signed and returned from the property owner. The City will be sending reminders to the remaining 43 property owners that they have until November 26th to return their signed proposals....

The City’s contractor Maggiora and Ghilotti has completed this project and the notice of completion should go before council in December.  

A new fence was installed this week around the North Francisco pump station. Prior to the fence being installed this area was became a gathering spot for IV drug users and homeless camps. The situation created a health and safety hazard for the public, as well as, the Department of Public Works and San Rafael...

The SMART Larkspur Extension construction work on the Francisco Blvd has been moving along steadily. West realignment and Phase-1 of the Multi-Use Path is starting to look like a street and a path.  The Contractor has paved from the 2nd Street intersection to where the new Rice Drive intersection will be.  It’s starting to look...

Project Progress During the month of September, Alten Construction substantially completed high roof steel erection and 1st Floor electrical and plumbing rough-in. High roof decking over the Apparatus Bay was started and completed. Work began on mechanical rough-in and framing for the 1st Floor, site-specific storm-drain, and Storage Building construction. PROJECT TEAM: Owner: City of San Rafael Project/Construction Manager:...

The City’s contractor M3 Integrated Services has been working on clearing and grubbing the future playground area. The contractor has begun demolition of the existing asphalt pathways and light standards. They are on schedule for a park dedication early next year.  

Project Progress During the month of September, Alten Construction substantially completed high roof steel erection and 1st Floor electrical and plumbing rough-in. High roof decking over the Apparatus Bay was started and completed. Work began on mechanical rough-in and framing for the 1st Floor, site-specific storm-drain, and Storage Building construction. PROJECT TEAM: Owner: City of San Rafael Project/Construction Manager:...

The Grand Ave bridge project is underway with excavation for the new bridge abutments on both the north and south sides of the San Rafael Canal. The Contractor uncovered buried concrete associated with a retaining wall at the former Marin Motors site. The City’s retained structural engineer reviewed the issues and the contractor is now...

Vallecito Child Care has a new addition to their facility. Our team removed old shed that was rotten and beyond repair. We built a new pier foundation for tough shed to install the unit and we included the front deck entrance to the shed for easy and convenient access.

In response to community interest in LPI, staff used the results of the County-wide Systemic Safety Analysis Report (SSAR) to select initial potential locations. Selected intersections in the downtown area have higher-than-average collision rates - compared to the state-wide average for similar facilities. The addition of LPI’s will allow the pedestrian phase to activate sooner...

The City’s contractor Hillside Drilling has completed the cast in drilled hole (CIDH) concrete piles and they have set the tieback anchors for the retaining wall at Tarrant court. The contractor has started tying rebar for the inside of the retaining wall.

The City’s contractor Valentine Corporation has nearly completed the work in the backyards on Glenaire Drive and they have started working on the third retaining wall on the hillside. The City is building a series of four retaining walls to stabilize the hillside and protect Irwin street during future winter storm.    

Fire Station #52  If you’ve driven by any of the Essential Facilities projects, you have seen the undeniable transformation that the City of San Rafael is going through. At Fire Station #52 the Training Tower, the Training Classroom and the Fire Station buildings are very close to completion. In the last few months, the contractor...

Close window