11/9/18 – SMART LARKSPUR EXTENSION UPDATE

Posted on November 9, 2018


The SMART Larkspur Extension construction work on the Francisco Blvd has been moving along steadily. West realignment and Phase-1 of the Multi-Use Path is starting to look like a street and a path.  The Contractor has paved from the 2nd Street intersection to where the new Rice Drive intersection will be.  It’s starting to look like a city street again!

The Multi-Use path (MUP) progress has slowed a bit, but still keeps moving forward.  SMART has begun installing base-rock for their tracks.  Work on the south-end of the MUP will be starting up next week.

Francisco Blvd West – looking north at intersection of Irwin Street.
Francisco Blvd West – looking north at intersection of Irwin Street.
Multi-Use Path – Phase-1 and Rail base rock; looking south.
Multi-Use Path – Phase-1 and Rail base rock; looking south.