Third Street Improvement Project – 03/03/2023 weekly update

Posted on March 3, 2023


The City of San Rafael will be sending out weekly project updates with construction updates, traffic

 closure updates, and other relevant information for this project. To receive these updates, please sign up using the form at the left-hand side of the project website.

THIS WEEK (February 27 – March 3):  

  • Construction crews replaced sanitary sewer lateral on Third Street from Lootens Place to A Street. 
  • Crews saw-cut pavement on Third Street from A Street to Lootens Place. This work required a lane closure on Third Street. 
  • Crews placed concrete for curb ramps at the northwest corners of Third Street and C Street, B Street and A Street.  
  • Crews potholed to locate storm drains at Second Street and G Street, and Third Street and B Street. 
  • Crews replaced a section of the sidewalk at 1654 Second Street. 
  • Crews shifted traffic lanes to the south on Second Street between Marquard Avenue and Shaver Street. 

NEXT WEEK (March 6 – March 10):  

  • Crews will continue replacing a section of sidewalk at 1654 Second Street. This work will require a lane closure and no parking on westbound Second Street.  
  • Crews will place concrete for curb ramps at the northwest corners of Third Street and C Street, and Third Street and B Street. This work will require curb lane closure and no parking adjacent to the intersections. 
  • Crews will replace storm drains at Second Street and G Street, and Third Street and B Street. This work will require curb lane closure and no parking adjacent to the intersections.
  • Crews will begin to construct the new median islands on Second Street from West Street to G Street. The work will require a lane closure and traffic lane shift. 
  • Crews will install and raise sidewalk pull boxes along Third Street. This work will require a curb lane closure during the installation of the pull boxes. 
  • Crews will replace the sanitary sewer lateral main on Third Street between A Street and Lootens Place. This work will require a lane closure on Third Street. 
  • Crews will replace the sanitary sewer lateral main on Third Street between Lincoln Avenue and Cijos Street. This work will require a lane closure on 3rd St. 

 IMPACTS:

  • The stairway from Second Street to Jessup Street (south of Ida Street) is closed.
  • For the lane shift on Second Street, the posted speed limit is 25 mph. Drivers should be aware of changed conditions and be alert.
  • Traffic Controls (temporary signs, message boards, traffic cones, delineators and detour signs) will be put in place to direct motorists through the work area.
  • Curb parking spaces will be marked “No Parking.”

The hours of work will be 6:00am – 6:00pm and lane closures 6:00am – 3:00pm on Third Street and Second Street westbound, and 9:00am – 6:00pm on Second Street eastbound.

Close window