Third Street Improvement Project – 04/28/2023 weekly update

Posted on April 28, 2023


The City of San Rafael will be sending out weekly project updates with construction updates, traffic

 closure updates, and other relevant information for this project. To receive these updates, please sign up using the form at the left-hand side of the project website.

 

 NIGHT WORK  APRIL 24-28  

Beginning April 24th, 2023, construction crews will be slip-lining the storm sewer pipe on Third Street between Grand Avenue and Irwin Street. This work will be performed at night (7:00pm to 6:00am).

THIS WEEK (April 24 – April 28)

  • Crews replaced sanitary sewer lateral on Ritter Street between Third Street and Lincoln Avenue.
  • Crews replaced sanitary sewer lateral on Third Street between Irwin Street and Grand Avenue. This work is being performed at night (6:00pm to 6:00am).
  • Crews plug paved at the new curb ramps along Third Street.
  • Crews removed and replaced concrete curb ramps at the southeast corner at Third Street and E Street.
  • Crews replaced the curb ramp at the southwest corner of Third Street and A Street.
  • Crews removed and replaced concrete curb ramps at the southwest corner at Third Street and Brooks Street.
  • Crews shifted traffic lanes to the south on Second Street between Marquard Avenue and Shaver Street.
  • Crews shifted traffic lanes northward on Third Street from C Street to E Street.

NEXT WEEK (May 1 – May 5): 

  • Crews will remove curb ramps at the southwest corners of Third Street and D Street and Third Street and E Street. This work will require a curb lane closure and no parking adjacent to the intersections.
  • Crews will construct the new curb ramp at the southwest corner of Third Street and Brooks Street. The work will require lane closure and a traffic lane shift.
  • Crews will construct a new Sanitation Department manhole at Third Street and Brooks Street. This work will require a lane closure.
  • Crews will replace the sanitary sewer lateral main on Ritter Street. This work will require a lane closure on Ritter Street.

IMPACTS:

  • For the next two weeks the Crews will replace sanitary sewer pipe on Third Street between Lincoln Avenue and Irwin Street. This work will be performed at night (7:00pm to 6:00am)
  • The stairway from Second Street to Jessup Street (south of Ida Street) is closed.
  • For the Lane Shift on Second Street, the posted speed limit is 25 mph. Drivers should be aware of changed conditions and be alert.
  • Traffic Controls (temporary signs, message boards, traffic cones, delineators and detour signs) will be put in place to direct motorists through the work area.
  • Curb parking spaces will be marked “No Parking.”

The hours of work will be 6:00am – 6:00pm and lane closures 6:00am – 3:00pm on Third Street and Second Street westbound, and 9:00am – 6:00pm on Second Street eastbound.

Close window