THIS WEEK (October 31 – November 4):

  • Construction crews formed the stairs and west end of the new retaining wall.
  • Crews installed drainpipe and backfill behind the retaining wall on Second Street.
  • Crews installed a catchment safety fence behind the retaining wall.
  • Crews replaced the sanitary sewer by open trench method on Second Street at Miramar Avenue.
  • Crews pulled wire for new signal poles and light poles at Second and Shaver Streets and Second and G Streets.
  • Crews poured foundation for signal poles and pedestrian push buttons at Third and A Streets.

NEXT WEEK (November 7 – November 11):

  • Crews will form and place rebar for the stairs and west end of the retaining wall.
  • Crews will continue installing a catchment fence along the top of the new retaining wall.
  • Crews will remove sections of pavement and median islands to construct bike lane separator islands. This work will require a lane closure and no parking on eastbound Second from Marquard to East Street. Also, West End Avenue will be blocked at Marquard, and a detour will be set up.
  • Crews will pull wire and set boxes for streetlights and signal lights at the intersection of Second & Fourth, Second & East, and Second & G Streets. This work will require a lane closure on westbound Second.
  • Crews will install splice boxes for new fiber optic cable on Third Street from Lootens to C Street. This work will require a lane closure and no curb parking.
  • Sanitary sewer rehabilitation: Crews will continue installing new sewer pipe and laterals by open trench method on Miramar Ave and Second Street. This work will require a lane closure on Miramar Avenue and on eastbound Second Street.
  • Crews will make repairs to sanitary sewer on Third Street between E Street and D Street. This work will require a closure of the center lane on Third Street

IMPACTS:

    • From November 7, 2022, to November 11, 2022, PG&E will be relocating electrical lines on Second Street from East Street to G Street. This work will require a lane closure on Second St between East Street and G Street
    • The stairway from Second Street to Jessup Street (south of Ida) is closed.
    • For the Lane Shift on Second Street the posted speed limit is 25 mph, drivers should be aware of changed conditions and be alert.
    • Traffic Controls (temporary signs, message boards, traffic cones, delineators and detour signs) will be put in place to direct motorists through the work area.
    • Curb parking spaces will be marked “No Parking.”

The hours of work will be 6:00am – 6:00pm and lane closures 6:00am – 3:00pm on Third Street and Second Street westbound, and 9:00am – 6:00pm on Second Street eastbound.