City Hall and other offices will be closed to the public from December 23 to January 3, but appointments are available upon request. Public safety and emergency services remain available 24/7.  

Third Street Improvement Project – 12/09/2022 weekly update

Posted on December 9, 2022


Third Street Photo 12/09/2022

The City of San Rafael will be sending out weekly project updates with construction updates, traffic closure updates, and other relevant information for this project. To receive these updates, please sign up using the form at the left-hand side of the project website.

THIS WEEK (December 5 – December 9):

  • Construction crews continue to form the stairs at the west end of the new retaining wall.
  • Crews backfilled behind the new retaining wall on Second Street.
  • Crews have removed sections of pavement and median islands to construct bike lane separator islands at the intersection of Second Street and Marquard Avenue.
  • Crews replaced the sanitary sewer on Third Street from D Street to C Street.
  • Crews installed new traffic signal controllers at Second Street and G Street, and at Second Street and Fourth Street.
  • Crews set pull boxes for new fiber optic cable on Third Street between Lootens Place and C Street.

NEXT WEEK (December 12 – December 16):

  • Crews will continue removing sections of pavement and median islands to construct bike lane separator islands.This work will require a lane closure and no parking on eastbound Second Street from West Street to G Street. Also, West End Avenue will be blocked at Marquard and a detour will be set up.
  • Crews will remove and replace the curb ramps at the intersection of Third Street and E Street. This work will require curb lane closure and no parking adjacent to the intersection.
  • Crews will install a new traffic signal controller at Second Street and East Street. This work will require curb lane closure and no curb parking.
  • Crews will pull wire to new pedestrian lights along Second Street.
  • Crews will install splice boxes for new fiber optic cable on Third Street. This work will require lane closure and no curb parking.
  • Crews will replace sanitary sewer laterals on Third Street between D Street and C Street. This work will require a closure of the center lane on Third Street.
  • Crews will replace the sanitary sewer main on Second Street between the intersection of Second Street and Third Street and Shaver Street. This work will require a lane closure on eastbound Second Street.

IMPACTS:

  • From December 12th to December 16th PG&E will be relocating electrical lines on G Street between Second Street and Fourth Street, and at Second Street and Marquard Street, and on Second Street from East Street to G Street. This work will require a lane closure on Second Street between East Street and G Street.
  • The stairway from Second Street to Jessup Street (south of Ida Street) is closed.
  • For the Lane Shift on Second Street the posted speed limit is 25 mph, drivers should be aware of changed conditions and be alert.
  • Traffic Controls (temporary signs, message boards, traffic cones, delineators and detour signs) will be put in place to direct motorists through the work area.
  • Curb parking spaces will be marked “No Parking.”

The hours of work will be 6:00am – 6:00pm and lane closures 6:00am – 3:00pm on Third Street and Second Street westbound, and 9:00am – 6:00pm on Second Street eastbound.

Close window