Third Street Improvement project – 3/18/22 weekly update

Posted on March 18, 2022


2022-03-18_Third Street Corridor Rehabilitation (3)

The City of San Rafael will be sending out weekly project updates with construction updates, traffic closure updates, and other relevant information for this project. To receive these updates, please sign up using the form at the left-hand side of the project website.


THIS WEEK (March 14 – 18): The City’s contractor, Maggiora & Ghilotti, worked on locating existing underground utilities and identifying potential utility conflicts on Third Street between Brooks Street and E Street.

Maggiora & Ghilotti also started installing water connections on Cijos Street, Ritter Street, and Lootens Place.

Ghilotti Bros. Inc., and St. Francis Electric began potholing to locate existing underground utilities at all the intersections for Second and Third Street between Marquard Avenue and Brooks Street.

NEXT WEEK (March 21- 25): Maggiora & Ghilotti will continue to trench and install the new Marin Municipal Water District (MMWD) waterline from Brooks Street to C Street and will continue to the west for the next month. Maggiora & Ghilotti will also be installing tie in connections in A Street and B Street. This work will require a lane closure on Third Street and detours on A Street, C Street, D Street, E Street, and Fourth Street.

Ghilotti Bros. Inc., and St. Francis Electric will continue potholing to locate existing underground utilities at all the intersections for Second and Third Street between Marquard Avenue and Brooks Street.

Ghilotti Bros. Inc., will also be performing vegetation work on Second and Third Street.

IMPACTS: Traffic Controls (temporary signs, message boards, traffic cones, delineators and detour signs) will be put in place to direct motorists through the work area. Curb parking spaces will be marked “No Parking.” There will be intermittent lane closures on Third Street and detours on A Street, C Street, D Street, E Street, and Fourth Street.

The hours of work will be 6:00am – 3:00pm. on Third Street and 9:00am – 6:00pm on Second Street.

For more information, visit the project website or contact the City at thirdstreet@cityofsanrafael.org.

Please note: all estimated timelines are tentative and subject to change.